Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A and B together do a job in 15 days and A alone could do the same job in 20 days. How many days would B take to do half the job if he worked alone?

A) 60 B) 30
C) 45 D) 40
 
Answer & Explanation Answer: B) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1356
Q:

A can do a work in 12 days while B can do it in 15 days. They undertake to complete it together for Rs. 450. what will be the share of A in this amount of money ?

A) Rs.200 B) Rs.240
C) Rs.250 D) Rs.300
 
Answer & Explanation Answer: C) Rs.250

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1351
Q:

Atul can do a piece of work in 18 days, Aaravya is 50% more efficient than Atul. How much more time does Atul take than Aaravya to do the same piece of work?

A) 12 B) 6
C) 18 D) 10
 
Answer & Explanation Answer: B) 6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1342
Q:

X does 25% of a work in 20 days. Y joins X and they together finish the remaining work in 15 days. Y alone can do the whole work in ___ days.

 

A) 30 days B) 25 1/2 days
C) 26 2/3 days D) 26 1/5 days
 
Answer & Explanation Answer: C) 26 2/3 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1337
Q:

Mayank, Deepak and Pawan, each of them working alone can complete a work in 5, 10 and 15 days respectively. If all three of them work together to complete a work and earn Rs. 12000 what will be Deepak's share of the earnings?

A) Rs. 2000 B) Rs. 6000
C) Rs. 4000 D) Rs. 3000
 
Answer & Explanation Answer: C) Rs. 4000

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1334
Q:

A can do a piece of work in 9 days while B can do it in 12 days. A and B together can do the work in

A) 5 1/7 days B) 5 2/7 days
C) 6 1/7 days D) 6 2/7 days
 
Answer & Explanation Answer: A) 5 1/7 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1333
Q:

24 men can do a piece of work in 17 days.How many men will be able to do it in 51 days ?

A) 8 B) 10
C) 12 D) 6
 
Answer & Explanation Answer: A) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1320
Q:

A and B can together do a piece of work in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is

A) 18 days B) 24 days
C) 9 days D) 12 days
 
Answer & Explanation Answer: A) 18 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1317