Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B and C finish it, working all together?

A) 6 days B) 5 1/4 days
C) 4 4/11 days D) 4 days
 
Answer & Explanation Answer: D) 4 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1317
Q:

P and Q can complete a task in 50 and 20 days respectively. In how many days can they complete 70% of the task if they work together?

A) 20 days B) 20 days
C) 40 days D) 10 days
 
Answer & Explanation Answer: D) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1317
Q:

P does half as much work as Q in 1/3 of the time. If together they take 15 days to complete a work, how many days will P take to do it alone?

 

A) 18   B) 25  
C) 24   D) 21
 
Answer & Explanation Answer: B) 25  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1308
Q:

Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. The ratio between the capacity of a man and a woman is

A) 3:4 B) 4:3
C) 5:3 D) 5:7
 
Answer & Explanation Answer: B) 4:3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1306
Q:

X can finish 25% of a work in a day. Y can do 12.5% of the same work in a day. In how many days, will both of them finish the work together?

A) 2.67 days B) 2.33 days
C) 3.33 days D) 3.67 days
 
Answer & Explanation Answer: A) 2.67 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1306
Q:

A man starts moving from a place A and reaches the place B in 26 hours. He covers 1/3rd of the distance at the speed of 4 km/hr and covers the remaining distance at the speed of 5 km/hr. What is the distance (in km) between A and B?

A) 45 B) 80
C) 120 D) 90
 
Answer & Explanation Answer: C) 120

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1302
Q:

Arun and Amit can do a piece of work in 9 days and 12 days respectively. If they work for alternate days and Amit starts the work first, then in how many days 35/36 parts of whole work will be completed?

A) 10 days B) 12 days
C) 5 days D) 8 days
 
Answer & Explanation Answer: A) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 1296
Q:

If 15 persons can do a job in 30 days, then 30 persons with twice the efficiency can do the same job in how many days?

A) 7 B) 3.5
C) 5 D) 7.5
 
Answer & Explanation Answer: D) 7.5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1294