FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

If A alone can do a job in 40 days then, in how many days can B alone do the job if together they can do the job in 8 days?

A) 15 B) 10
C) 20 D) 25
 
Answer & Explanation Answer: B) 10

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 647
Q:

Arjun and Anurag complete a job in 6 days and 7 days respectively. They worked together and earned a total of Rs. 780. Find Arjun's share in this amount in Rs. ?

A) 490 B) 560
C) 350 D) 420
 
Answer & Explanation Answer: D) 420

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 643
Q:

B is thrice as efficient as A and C is 0.75 times as efficient as A. What is the ratio of number of days taken by A, B and C when they work individually?

A) 4:1:3 B) 3:1:4
C) 2:3:1 D) 5:1:2
 
Answer & Explanation Answer: B) 3:1:4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 632
Q:

A can do a work in 15 days and B in 20 days. If they work on it together for 6 days, then what fraction of work is left?

A) 1/4 B) 2/9
C) 1/5 D) 3/10
 
Answer & Explanation Answer: D) 3/10

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 625
Q:

Rahul can complete a work in 18 days and Sonu can complete the same work in 15 days. If both together work for 5 days, then what part of total work is left?

 

A) 7/15 B) 11/18
C) 7/18 D) 8/15
 
Answer & Explanation Answer: C) 7/18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 614
Q:

X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part  of the total work?

 

A)  6 B) 4
C) 3 D) 12
 
Answer & Explanation Answer: B) 4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 603
Q:

Arun and Amit can do a piece of work in 9 days and 12 days respectively. If they work for alternate days and Amit starts the work first, then in how many days 35/36 parts of whole work will be completed?

A) 10 days B) 12 days
C) 5 days D) 8 days
 
Answer & Explanation Answer: A) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 594
Q:

S does half as much work as T in 1/7 of the time taken by T. If together they take 21 days to complete a work, then how may days shall S take to complete that work alone?

 

 

A) 26   B)  27  
C) 28   D) 32
 
Answer & Explanation Answer: B)  27  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work