Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?

A) 4 days B) 8 days
C) 3 days D) 6 days
 
Answer & Explanation Answer: D) 6 days

Explanation:

4/10 + 9/x = 1     => x = 15 

 

Then both can do in 

1/10 + 1/15 = 1/6     => 6 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

19 16439
Q:

4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it ?

A) 40 days B) 36 days
C) 32 days D) 34 days
 
Answer & Explanation Answer: A) 40 days

Explanation:

Let 1 man's 1 day work = x and 1 woman's 1 day work = y.
Then, 4x + 6y = 1/8 and 3x + 7y = 1/10
Solving these two equations, we get:
x = 11/400 and y = 1/400
10 woman's 1 day work = (1/400 x 10) = 1/40.

Hence, 10 women will complete the work in 40 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

19 15966
Q:

After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?

A) 24.5 days B) 26.6 days
C) 25 days D) 20 days
 
Answer & Explanation Answer: B) 26.6 days

Explanation:

Arun has completed 13rd of the work in 8 days

Then he can complete the total work in

13 ---- 8

 1 ---- ?

= 24 days


But given Akhil is only 60% as efficient as Arun

Akhil =124×60100=140

Akhil can complete the total work in 40 days

Now, remaining 2/3rd of work can be completed in

 1  ------   40

23 ------   ?  

= 26.66 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

18 9564
Q:

P alone can do a piece of work in 24 days. The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work. How many days are required to complete by P and Q working together ?

A) 9 3/5 days B) 7 days
C) 6 3/7 days D) 8 days
 
Answer & Explanation Answer: A) 9 3/5 days

Explanation:

Let the total work be 'W'

As per the given information,

P can complete the work 'W' in 24 days.

=> one day work of P = W/24

And also given that,

The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work

=> PW/3 = QW/2

=> P's

1 day =    W/24

   ?    =      W/3

=>  ?  = 24W/3W  = 8

=> QW/2 = 8 days

=> Q alone can complete the work W in 16 days

=> P + Q can complete the work in

1/24 + 1/16 = 5/48

=> 48/5 days = 9 3/5 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

18 8003
Q:

12 men complete a work in 9 days. After they have worked for 6 days, 4 more men join them. How many days will they take to complete the remaining work ?

A) 2 days B) 2.5 days
C) 2.25 days D) 3 days
 
Answer & Explanation Answer: C) 2.25 days

Explanation:

1 man's 1 day work = 1/108
12 men's 6 day's work = 1/9 x 6 = 2/3

Remaining work = 1 - 2/3 = 1/3

16 men's 1 day work = 1/108 x 16 = 4/27
4/27 work is done by them in 1 day.

1/3 work is done by them in 27/4 x 1/3 = 9/4 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

18 13107
Q:

P, Q, and R can do a job in 12 days together.  If their efficiency of working be in the ratio 3 : 8 : 5, Find in what time Q can complete the same work alone?

A) 36 days B) 30 days
C) 24 days D) 22 days
 
Answer & Explanation Answer: A) 36 days

Explanation:

Given the ratio of efficiencies of P, Q & R are 3 : 8 : 5

Let the efficiencies of P, Q & R be 3x, 8x and 5x respectively

They can do work for 12 days.

=> Total work = 12 x 16x = 192x

 

Now, the required time taken by Q to complete the job alone = 162x8x = 24 days.

Report Error

View Answer Report Error Discuss

17 11613
Q:

A can do 50% of the job in 16 days, B can do 1/4th of the job in 24 days. In how many days can they do 3/4th of the job working together?

A) 24 B) 9
C) 21 D) 18
 
Answer & Explanation Answer: D) 18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

17 2104
Q:

P is 30% more efficient than Q. How much time will they, working together, take to complete a job which P alone could have done in 23 days?

A) 16 days B) 13 days
C) 15 days D) 12 days
 
Answer & Explanation Answer: B) 13 days

Explanation:

Ratio of times taken by P & Q = 100 : 130 = 10:13

 

Let Q takes x days to do the work

Then, 10:13 :: 23:x

=> x = 23x13/10

=> x = 299/10

 

P's 1 day's work = 1/23

Q's 1 day's work = 10/299

(P+Q)'s 1 day's work = (1/23 + 10/299) = 23/299 = 1/13

Hence, P & Q together can complete the work in 13 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

17 15191