Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A and B can do a piece of work for Rs 1540. Find the difference between the wages of C and B for the same work If A can do the work in 12 days and B can do the same work in 8 days and with the help of C, A and B can do the same work in 2 days?

A) 980 B) 1232
C) 810 D) 1121
 
Answer & Explanation Answer: B) 1232

Explanation:

From the given data,


                       Day      Capacity

A              ->    12          2

B              ->     8           3             2

A + B + C ->     2            12

=> Capacity of C = 12 - 5 = 7

Ratio of capacity of A : B : C = 2 : 3 : 7

Difference of wages of C & B = 4/5 x 1540

= 4 x 308 = Rs. 1232

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

13 4366
Q:

Priya can do a work in 16 days. In how many days will the work be completed by Sai, if the efficiency of Sai is 60% more than that of Priya ?

A) 8 days B) 12 days
C) 14 days D) 10 days
 
Answer & Explanation Answer: D) 10 days

Explanation:

Ratio of efficiencies of Priya and Sai is

Sai : Priya = 160 : 100 = 8 : 5

Given Priya completes the work in 16 days

Let number of days Sai completes the work be 'd'

=> 5×16 = 8×d

d = 10 days.

Therefore, number of days Sai completes the work is 10 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

13 4262
Q:

6 boys and 8 girls can do job in 10 days , 26 boys & 48 women do work in 2 days. Find time taken by 15 boys and 20 girls to do same work ?

A) 2 days B) 3 days
C) 4 days D) 5 days
 
Answer & Explanation Answer: C) 4 days

Explanation:

One day work of 6 boys and 8 girls is given as 6b + 8g = 1/10 -------->(I)

 


One day work of 26 boys and 48 women is given as 26b + 48w = 1/2 -------->(II)

 

Divide both sides by 2 in (I) and then multiply both sides by 5

Now we get, 15b + 20g = 1/4.

Therefore, 15 boys and 20 girls can do the same work in 4 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

13 11023
Q:

If 34 men completed 2/5th of a work in 8 days working 9 hours a day. How many more man should be engaged to finish the rest of the work in 6 days working 9 hours a day ? 

A) 101 men B) 112 men
C) 102 men D) 120 men
 
Answer & Explanation Answer: C) 102 men

Explanation:

From the above formula i.e (m1 x t1/w1) = (m2 x t2/w2)

so, [(34 x 8 x 9)/(2/5)] = [(M x 6 x 9)/(3/5)]

so, M = 136 men

 

Number of men to be added to finish the work = 136-34 = 102 men.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

13 11101
Q:

A and B can complete a task in 1.5 days. However, A had to leave a few days before the task wascompleted and hence it took 2 days in all to complete the task. If A alone could complete the work in2.625 days, how many days before the work getting over did A leave?

A) 1.125 B) 0.625
C) 0.375 D) 0.875
 
Answer & Explanation Answer: D) 0.875

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

13 1563
Q:

Twenty men can do a work in eighteen days. Eighteen women can complete the same work in fifteen days. What is the ratio between the capacity of a woman and a man ?

A) 4:5 B) 3:4
C) 4:3 D) 2:3
 
Answer & Explanation Answer: C) 4:3

Explanation:

(20 x 18) men can complete the work in in one day.

one man's one day work = 1/360

(18 x 15) women can complete the work in 1 day

1 woman's one day work = 1/270

So, required ratio = 1270:1360= 4:3

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

13 7997
Q:

K can build a wall in 30 days. L can demolish that wall in 60 days. If K and L work on alternate days, when will the wall be completed ?

A) 120 days B) 119 days
C) 118 days D) 117 days
 
Answer & Explanation Answer: D) 117 days

Explanation:

K's work in a day(1st day) = 1/30
L's work in a day(2nd day)= -1/60(demolishing)
hence in 2 days, combined work= 1/30 - 1/60 =1/60
since both works alternatively, K will work in odd days and L will work in even days.
1/60 unit work is done in 2 days
58/60 unit work will be done in 2 x 58 days = 116 days
Remaining work = 1-58/60 = 1/30
Next day, it will be K's turn and K will finish the remaining 1/30 work.
hence total days = 116 + 1 = 117.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

12 7390
Q:

A tank has an inlet and outlet pipe. The inlet pipe fills the tank completely in 2 hours when the outlet pipe is plugged. The outlet pipe empties the tank completely in 6 hours when the inlet pipe is pluggeed.

If there is a lekage also which is capable of draining out the liquid from the tank at half of the  rate of outet pipe,them what is the time taken to fill the emty tank when both the pipes are opened?

A) 3 hours B) 4 hours
C) 5 hours D) None of these
 
Answer & Explanation Answer: B) 4 hours

Explanation:

Rate of leakage = 8.33% per hour

Net efficiency = 50 - (16.66 + 8.33)= 25%

Time required = 100/25 = 4 hours

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

12 10340