Questions

Q:

What movement tried to end racial discrimination?

A) The Negro movement B) The Chipko movement
C) The Civil Rights movement D) The Feminist movement
 
Answer & Explanation Answer: C) The Civil Rights movement

Explanation:

The Civil Rights Movement :

 

The Civil Rights Movement in the United States was a struggle by black Americans to gain full citizenship rights and achieve racial equality.

Individuals and organizations challenged discrimination with a variety of activities, including protest marches, boycotts, and refusal to abide by segregation laws.

Many believe that the movement began with the bus boycott in Montgomery, Alabama, in 1955 and ended with the Voting Rights Act of 1965.

Report Error

View Answer Report Error Discuss

Filed Under: World History
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2904
Q:

RAM stands for

A) Relative Atomic Memory B) Random Altered Memory
C) Random Access Memory D) Relative Altered memory
 
Answer & Explanation Answer: C) Random Access Memory

Explanation:

RAM stands for Random Access Memory.

Report Error

View Answer Report Error Discuss

4 2904
Q:

What process immediately preceeded protein synthesis at the ribosome?

A) transcription B) replication
C) translation D) duplication
 
Answer & Explanation Answer: A) transcription

Explanation:

Protein synthesis at the ribosome is immediately preceeded by the transcription process.

Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk

3 2904
Q:

What is logical link control?

Answer

One of two sublayers of the data link layer of OSI reference model, as defined by the IEEE 802 standard. This sublayer is responsible for maintaining the link between computers when they are sending data across the physical network connection

Report Error

View answer Workspace Report Error Discuss

Subject: Networking
Job Role: Network Engineer

0 2903
Q:

Project Risk Management

What are the Project Management Processes included in the Project Risk Management? 

Answer

The Project Risk Management Processes include the following:


Risk Management Planning - Deciding how to approach , plan, and execute the risk management activities for a project


Risk Identification - Determining which risks might affect the project and documenting their characteristics.


Qualitative Risk Analysis - Prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact


Quantitative Risk Analysis - Numerically analyzing the effect on overall project objectives of identified risks


Risk Response Planning - Developing options and actions to enhance opportunities , and to reduce threats to project objectives.


Risk Monitoring and Control - Tracking identified risks, monitoring residual risks, identifying new risks, executing risk response plans, and evaluating their effectiveness throughout the project life cycle.

Report Error

View answer Workspace Report Error Discuss

0 2903
Q:

Red Indians called this local wind  Ice Eater?

A) Mistral B) Chinook
C) Foehn D) Haramattan
 
Answer & Explanation Answer: B) Chinook

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Geography

1 2902
Q:

Which of the following are true of meditation in buddhism?

A) Right concertation is reached through meditation B) It can involve concetration on your breathing
C) It can mean visualizing certain things D) All of the above
 
Answer & Explanation Answer: D) All of the above

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank PO

0 2901
Q:

The book ' Redesigning the Aeroplane While Flying : Reforming Institutions' is written by

Answer

Arun Maira

Report Error

View answer Workspace Report Error Discuss

5 2900