Certification Questions

Q:

If a hub has three computers connected to it, how many broadcast and collision domains is the hub creating?

A) Three broadcast and one collision B) Three broadcast and three collision
C) one broadcast and three collision D) One broadcast and one collision
 
Answer & Explanation Answer: D) One broadcast and one collision

Explanation:

If a hub has three computers connected to it, one broadcast and one collision domain is created

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 5548
Q:

Which three IP addresses can be assigned to hosts if the subnet mask is /27 and subnet zero is usable?

A. 10.15.32.17
B. 17.15.66.128
C. 66.55.128.1
D. 135.1.64.34
E. 129.33.192.192
F. 192.168.5.63

Answer

Answer : A C D


 


 


 


Explanation: If you follow the cram table,  /27 is mask 255.255.255.224. 3 bits were borrowed with value of 32. Follow the fourth octets of the addresses:
A is a usable host address.
B is classified as a network address
C is a usable host address form the subnet 0
D is a usable host address
E is a network address
F is a broadcast address

Report Error

View answer Workspace Report Error Discuss

Subject: CCNA

16 5500
Q:

Typically not referred to as a buffer type in critical chain project management is ______.

A) Free Buffer B) Resource Buffer
C) Project Buffer D) Feeding Buffer
 
Answer & Explanation Answer: A) Free Buffer

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

18 5497
Q:

The primary goal of financial management is to

A) Expand their share of the market B) Maximize the current value per share of the existing stock
C) Examining whether costs are reasonable or unreasonable D) All the above
 
Answer & Explanation Answer: B) Maximize the current value per share of the existing stock

Explanation:

The primary goals of financial management dwell on both short-term and long-term activities that seek to maximize value creation from scarce financial resources. And then the primary goal of financial management is to Maximize the current value per share of the existing stock.

 

All businesses aim to maximize their profits, minimize their expenses and maximize their market share. Here is a look at each of these goals.

 

Financial management is a process that enables a business to plan, direct, organize, monitor and control its current and future financial resources and events. It involves applying the basic principles of management in financial activities such as purchases, sales, capital expansion, inventory valuation, financial reporting, and profit distribution.

Report Error

View Answer Report Error Discuss

Filed Under: SAP FI
Exam Prep: Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

11 5445
Q:

Which of the following is not true about bottom-up estimating?

A) The WBS must be accurate and complete before this process can be used. B) Since the cost is largely independent of the desired accuracy it is the methodology of choice.
C) Its accuracy increases if the activities are smaller. D) It is not a useful methodology in the early project planning phase.
 
Answer & Explanation Answer: B) Since the cost is largely independent of the desired accuracy it is the methodology of choice.

Explanation:

“The cost and accuracy of bottom-up cost estimating is typically influenced by the size and complexity of the individual activity or work package.” PMBOK [7.1.2.4]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 5409
Q:

A switch has been configured configured for three different VLANs : VLAN2, VLAN3 and VLAN4. A router has been added to provide communication between the VLANs. What minimum type of interface necessary on the router if only one connection is to be made between the router and the switch?

A) 10Mbps Ethernet B) 56Kbps Serial
C) 100Mbps Ethernet D) 1Gbps Ethernet
 
Answer & Explanation Answer: C) 100Mbps Ethernet

Explanation:

Although you can use either 100Mbps or 1Gbps Ethernet, the 100Mbps is necessary at a minimum and is the best answer to this question. You need to trunk the link from the switch to the router to make this connection work with inter-VLAN communication.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 5406
Q:

 What is the difference between a process and a project?

A) A process is continuous and has no end date, whereas a project has a finite lifespan. B) A project is continuous and has no end date, whereas a process has a finite lifespan.
C) A process stops when the objective has been achieved, whereas a project does not stop when the objective is met. D) In a project the focus is not on the result, whereas with a process the result is important
 
Answer & Explanation Answer: A) A process is continuous and has no end date, whereas a project has a finite lifespan.

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: ITIL Certification

0 5391
Q:

A wireless client cannot connect to an 802.11b/g BSS with a b/g wireless card. The client section of the access point does not list any active WLAN clients. What is a possible reason for this?

A) The incorrect channel is configured on the client B) The Client's IP address is on the wrong subnet
C) The client has an incorrect pre-shared key D) The SSID is configured incorrectly on the client
 
Answer & Explanation Answer: D) The SSID is configured incorrectly on the client

Explanation:

Although this question is cryptic at best, the only possible answer is option D. If the  SSID is not being broadcast (which we must assume in this question), the client must be configured with the correct SSID in order to associate to the AP.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 5380