Certification Questions

Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 5252
Q:

What is the purpose of the DHCP server?

A - to provide storage for email
B - to translate URLs to IP addresses
C - to translate IPv4 addresses to MAC addresses
D - to provide an IP configuration information to hosts

Answer

Answer : D


Explanation:The main purpose of the DHCP server is to provide IP configuration parameters to hosts such as the default gateway, domain name, Domain Name System – DNS .

Report Error

View answer Workspace Report Error Discuss

Subject: CCNA

4 5243
Q:

You have a computer named Computer1 that runs Windows Vista and a computer named Computer2 that runs Windows 7. You plan to migrate all profiles and user files from Computer1 to Computer2.


You need to identify how much space is required to complete the migration.
What should you do?

A) On Computer1 run Loadstate c:\store /nocompress B) On Computer1 run Scanstate c:\store /nocompress /p
C) On Computer2 run Loadstate \\computer1\store /nocompress D) On Computer2 run Scanstate \\computer1\store /nocompress /p
 
Answer & Explanation Answer: B) On Computer1 run Scanstate c:\store /nocompress /p

Explanation:
Report Error

View Answer Report Error Discuss

24 5242
Q:

You have a computer that runs Windows 7.


A printer is installed on the computer.


You remove the Everyone group from the access control list (ACL) for the printer, and then you share the printer. You need to ensure that members of the Sales group can modify all the print jobs that they submit.


You must prevent Sales group members from modifying the print jobs of other users.
What should you do?

A) From the printer's properties, assign the Print permission to the Sales group. B) From the printer's properties, assign the Manage Documents permission to the Sales group.
C) From the local Group Policy, assign the Increase scheduling priority user right to the Sales group. D) From the local Group Policy, assign the Take ownership of files or other objects user right to the Sales group.
 
Answer & Explanation Answer: A) From the printer's properties, assign the Print permission to the Sales group.

Explanation:
Report Error

View Answer Report Error Discuss

15 5231
Q:

One of the goals of management by objectives (MBO) is to ensure that objectives of one level within an organization are supportive of and aligned with the objectives of another level of the organization. This methodology has been popular within some organizations as they define their culture. Which of the following is not true about MBO?

A) It has a top-down orientation B) Corrective actions are not part of the process
C) You need to establish clear and achievable objectives D) MBO is a natural fit for Project Management
 
Answer & Explanation Answer: B) Corrective actions are not part of the process

Explanation:

Corrective actions are part of the process after establishing objectives and checking on the objectives. The next step is to take corrective actions. Answers A, C, D are true statements and therfore are incorrect for this question.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 5156
Q:

The Acme Corporation is implementing dail-up services to enable remote-office employees to connect to the local network. The company uses multiple routed protocols,needs authentication of users connecting to the network, and since some calls will be long distance, needs callback support. Which of the following protocols is the best choice for these remote services? 

A) 802.1 B) Frame Relay
C) HDLC D) PPP
 
Answer & Explanation Answer: D) PPP

Explanation:

PPP is your only option because HDLC and Frame RElay do not support these types of business requirements. PPP provides dynamic addressing , authentication using PAP or CHAP, and callback services.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 5133
Q:

How many non- overlapping channels are available with 802.11b?

A) 3 B) 12
C) 23 D) 40
 
Answer & Explanation Answer: A) 3

Explanation:

The IEEE 802.11b standard provides three non-overlapping channels.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

2 5127
Q:

If you want to have more than one Telnet session open at the same time, what keystroke combination would you use?

A) Tab+spacebar B) Ctrl+X, then 6
C) Ctrl+Shift+X, then 6 D) Ctrl+Shift+6, then X
 
Answer & Explanation Answer: D) Ctrl+Shift+6, then X

Explanation:

To keep open one or more Telnet sessions, use the Ctrl+Shift+6 and then X keystroke combination.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 5127