Q:

An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

A) Additional resources using the contingency fund B) Escalation approval to use contingency funding
C) Team overtime to meet schedule D) Corrective action based on causes
 
Answer & Explanation Answer: D) Corrective action based on causes

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

37 21319
Q:

Function GWT is used in time valuation to select time wage types for all absences, which are valued on the basis of the As If principle

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

Subject: SAP HR

18 21263
Q:

Which of the following is NOT an objective of service transition ?

A) To plan and manage the capacity and resource requirements to manage a release B) To provide quality knowledge and information about services and service assets
C) To provide training and certification in project management D) To ensure that a service can be operated, managed and supported
 
Answer & Explanation Answer: C) To provide training and certification in project management

Explanation:
Report Error

View Answer Report Error Discuss

15 20926
Q:

What command will permit SMTP mail to only host 1.1.1.1?

A) access-list 10 permit smtp host 1.1.1.1 B) access-list 110 permit ip smtp host 1.1.1.1
C) access-list 10 permit tcp any host 1.1.1.1 eq smtp D) access-list 110 permit tcp any host 1.1.1.1 eq smtp
 
Answer & Explanation Answer: D) access-list 110 permit tcp any host 1.1.1.1 eq smtp

Explanation:

when trying to find the best answer to an access - list question, always check the access - list bnumber and then the protocol. When filtering to an upper - layer protocol, you must use an extended list, numbers 100 - 199 and 2000 - 2699. Also, when you filter to the port of an upper - layer protocol, you must use either tcp or udp in the ACL protocol field. If it says ip in the protocol field, you cannot filoter on the port number of an upper - layer protocol. SMTP uses TCP

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

23 20896
Q:

Routers operate at layer _____. LAN switches operate at layer ______. Ethernet hubs operate at layer _____. Word processing operates at layer _______.

A) 3, 3, 1, 7 B) 3, 2, 1, none
C) 3, 2, 1, 7 D) 3, 3, 2, none
 
Answer & Explanation Answer: B) 3, 2, 1, none

Explanation:

Routers operate at layer 3. LAN switches operate at layer 2. Ethernet hubs operate at layer 1. Word processing applications communicate to the Application layer interface, but do not operate at layer 7, so the answer would be none.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

31 20162
Q:

Proxy servers have two main purposes :

1. Improve Performance  (and)

2.  is  ______ ?

A) Transmit Request B) Decrease Requests
C) Increase Requests D) Filter Requests
 
Answer & Explanation Answer: D) Filter Requests

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: IBM Certification

33 20020
Q:

A relational database developer refers to a record as

A) a relation B) an attribute
C) a criteria D) a tuple
 
Answer & Explanation Answer: D) a tuple

Explanation:

A relational database developer refers to a record as a tuple.

Report Error

View Answer Report Error Discuss

41 19925
Q:

What is the main reason for establishing a baseline?

A) For knowing the cost of services provided B) For roles and responsibility to be clear
C) To standardize operation D) For later comparison
 
Answer & Explanation Answer: D) For later comparison

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: ITIL Certification

6 19897