Certification Questions

Q:

The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?

A) Performance management B) Scope identification
C) Risk identification D) Project team status meeting
 
Answer & Explanation Answer: C) Risk identification

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

26 18783
Q:

 What does Mean Time to Repair (MTTR) mean?

A) Average uptime of a service B) Average downtime of a service
C) Average time between two consecutive incidents D) Average time of the breakdown-free period within a measured period
 
Answer & Explanation Answer: B) Average downtime of a service

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: ITIL Certification

16 18017
Q:

An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

A) Additional resources using the contingency fund B) Escalation approval to use contingency funding
C) Team overtime to meet schedule D) Corrective action based on causes
 
Answer & Explanation Answer: D) Corrective action based on causes

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

37 17328
Q:

What command will permit SMTP mail to only host 1.1.1.1?

A) access-list 10 permit smtp host 1.1.1.1 B) access-list 110 permit ip smtp host 1.1.1.1
C) access-list 10 permit tcp any host 1.1.1.1 eq smtp D) access-list 110 permit tcp any host 1.1.1.1 eq smtp
 
Answer & Explanation Answer: D) access-list 110 permit tcp any host 1.1.1.1 eq smtp

Explanation:

when trying to find the best answer to an access - list question, always check the access - list bnumber and then the protocol. When filtering to an upper - layer protocol, you must use an extended list, numbers 100 - 199 and 2000 - 2699. Also, when you filter to the port of an upper - layer protocol, you must use either tcp or udp in the ACL protocol field. If it says ip in the protocol field, you cannot filoter on the port number of an upper - layer protocol. SMTP uses TCP

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

23 16916
Q:

Which of the following is NOT an objective of service transition ?

A) To plan and manage the capacity and resource requirements to manage a release B) To provide quality knowledge and information about services and service assets
C) To provide training and certification in project management D) To ensure that a service can be operated, managed and supported
 
Answer & Explanation Answer: C) To provide training and certification in project management

Explanation:
Report Error

View Answer Report Error Discuss

15 16784
Q:

Routers operate at layer _____. LAN switches operate at layer ______. Ethernet hubs operate at layer _____. Word processing operates at layer _______.

A) 3, 3, 1, 7 B) 3, 2, 1, none
C) 3, 2, 1, 7 D) 3, 3, 2, none
 
Answer & Explanation Answer: B) 3, 2, 1, none

Explanation:

Routers operate at layer 3. LAN switches operate at layer 2. Ethernet hubs operate at layer 1. Word processing applications communicate to the Application layer interface, but do not operate at layer 7, so the answer would be none.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

30 16178
Q:

Proxy servers have two main purposes :

1. Improve Performance  (and)

2.  is  ______ ?

A) Transmit Request B) Decrease Requests
C) Increase Requests D) Filter Requests
 
Answer & Explanation Answer: D) Filter Requests

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: IBM Certification

33 15893
Q:

A relational database developer refers to a record as

A) a relation B) an attribute
C) a criteria D) a tuple
 
Answer & Explanation Answer: D) a tuple

Explanation:

A relational database developer refers to a record as a tuple.

Report Error

View Answer Report Error Discuss

41 15861