Q:

A project charter is one of the key deliverables to come from the initiation process. The project charter should by issued by 

A) one or more functional managers B) The head of the performing organization
C) A manager external to the project D) The CFO
 
Answer & Explanation Answer: C) A manager external to the project

Explanation:

The other answers could be accurate in specific situations, but their role alone does not meet the keyb criterion of being "external" to the project team. Answers A, B, and D are incorrect because these individuals are not external to the project.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4140
Q:

Which of the following best describes how the user is alerted with information system and configuration alerts?

A) A popup occurs and the Windows 7 desktop contrast is dimmed. Until you acknowledge the alert the screen will not move. B) If Aero is installed the shaking alert flag appears in the index bar of every open window.
C) A flag in the taskbar with a red D) All of the above
 
Answer & Explanation Answer: C) A flag in the taskbar with a red

Explanation:
Report Error

View Answer Report Error Discuss

4 4128
Q:

The currency of the controlling area must always be the same as the currency of the company code.

A) TRUE B) FALSE
Answer & Explanation Answer: B) FALSE

Explanation:

In cross-company assignments, every company code can be processed in its own currency. You are free to select the controlling area currency.

Report Error

View Answer Workspace Report Error Discuss

Subject: SAP CO

1 4124
Q:

When creating a pool of global address, which of the following can be used instead of the netmask command?

A) / (slash notation) B) prefix - length
C) no mask D) block - size
 
Answer & Explanation Answer: B) prefix - length

Explanation:

Instead of the netmask command, you can use the prefix-length length statement.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 4108
Q:

You want to improve network performance by increasing the bandwidth available to hosts and limit the size of the broadcast domains. Which of the following options will achieve this goal?

A) Managed hubs B) Bridges
C) Switches D) Switches configured with VLANs
 
Answer & Explanation Answer: D) Switches configured with VLANs

Explanation:

By creating and implementing VLANs in your switched network, you can break up broadcast domains at layer2. For hosts on different VLANs to communicate, you must have a router or layer 3 switch. 

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 4105
Q:

We must settle all line items at once, and you do not have to distribute100 percent of each line item for AUC using line item settlement.

A) TRUE B) FALSE
Answer & Explanation Answer: B) FALSE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

Subject: SAP FI

0 4105
Q:

Sometimes project managers forget all of the expenses that they can incur on a project, such as capital resources and assets. This can have an impact upon their budgets and the economic return on the project. A cost that has been incurred and cannot be reversed is known as a 

A) Fixed Cost B) Direct Cost
C) Variable Cost D) Sunk Cost
 
Answer & Explanation Answer: D) Sunk Cost

Explanation:

Answer D is correct because a sunk cost is a project expense that will eventualy need to be paid. Answer A is incorrect because a fixed cost remains constant, regardless of any change in a company's activity. Answer B is incorrect because direct cost can be directly linked to producing specific goods or services. Answer C is incorrect because a variable cost changes in proportion to a change in the company's activity or business.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4099
Q:

What are some recommendations for increasing Quality Score for a keyword?

Answer

Edit the ad associated with that keyword and direct users to a landing page that is very relevant.

Report Error

View answer Workspace Report Error Discuss

13 4089