Q:

Which of the following tools is used to create subscription sets and add subscription?set members to subscription sets?

A) Journal B) License Center
C) Replication Center D) Development Center
 
Answer & Explanation Answer: C) Replication Center

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: IBM Certification

1 2576
Q:

Which IEEE committee has been sanctioned by WAP and is called WPA2?

Answer

The IEEE 802.11i standard has been sanctioned by WPA and is termed WPA version 2.

Report Error

View answer Workspace Report Error Discuss

Subject: CCNA

1 2575
Q:

Navigation structure of roadmanps consist of

A. work packages            B. tasks

C. accelerators                D.phases

E. activities

Report Error

View answer Workspace Report Error Discuss

9 2572
Q:

Identify the actual value flows that can be analyzed using the value field analysis function.

A. Incoming sales orders from Sales and Distribution

B. A Transfer of billing documents

C. Actualcosts

D. Direct postings from Financial Accounting and Materials management

Answer

Answer : A , B , D


 


Explanation : The value field analysis function enables you to analyze the actual value flows, such as transfer of billing documents, incoming sales orders from Sales and Distribution, direct postings from Financial Accounting and Materials Management, and external data transfer.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

0 2568
Q:

If someone in Russia sets their language preference to English, will they see ads targeted to people in Russia? Will their ads be in Russian or in English?

Answer

They will see ads targeted to people located in Russia with the ads in English.

Report Error

View answer Workspace Report Error Discuss

1 2568
Q:

Project authorization is one of the processes that is associated with the initiation phase of a project. Authorization can come in many different forms, and projects are generally authorized by all of the following except

A) Technological Advances B) Customer request or market demand
C) Executive year - end bonuses D) Business or Social needs
 
Answer & Explanation Answer: C) Executive year - end bonuses

Explanation:

Project authorization should not be exclusively based upon the impact of an executive's bonus (many people would agree that it should not ever be based upon an executive's bonus). Answer A, B, and D are common events that predicate the need for project authorization and can evolve into large scope projects.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 2565
Q:

Which three entries have to be made to define the overhead structure completely?

A. Accrual object(s)                     B. Overhead rates

C. Deferral object(s)                   D. Base cost element(s)

E. Overhead element(s)

Answer

Answer : A , B , D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

1 2564
Q:

What is the Purpose of a Project Charter?

Answer

 


1. Project Charter refers to a statement of objectives in a project.


 
2. It provides a preliminary delineation of roles and responsibilities, outlines the project objectives, identifies the main stakeholders, and defines the authority of the project manager.


 
3. It serves as a reference of authority for the future of the project. The terms of reference are usually part of the project charter.

Report Error

View answer Workspace Report Error Discuss

10 2563