Certification Questions

Q:

What is XPath?

Answer

XPath is an expressions to select a xml node in an XML document.


It allows the navigation on the XML document to the straight to the element where we need to reach and access the attributes.


 

Report Error

View answer Workspace Report Error Discuss

1 2368
Q:

[CO-OM-CCA] When a cost center is created, certain basic data must be entered. Which of the following are needed when creating a cost center.

A. Assignment to company code          B. Validity period

C. Assignment to cost element            D. Selection of activity unit

E. Cost center category

Answer

Answer : A , B , E

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

0 2367
Q:

What help ensure that the XIV Systems cache does not become a bottleneck?

A) central cache locking mechanism B) use of industry standard chip technology
C) each module is responsible for caching the data in that module D) having all modules understand what is held cache at all times
 
Answer & Explanation Answer: C) each module is responsible for caching the data in that module

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: IBM Certification

1 2365
Q:

Why is it a bad idea to duplicate keywords in multiple Ad Groups?

Answer

Keywords in multiple ad groups compete against each other, and the keyword with the higher performance will trigger the ad in that Ad Group to run.

Report Error

View answer Workspace Report Error Discuss

0 2364
Q:

Project Management - Introduction

What is Portfolio Management?

Answer

A Portfolio is a collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives.

Report Error

View answer Workspace Report Error Discuss

0 2360
Q:

At which point can goods issue be posted if qualitiy inspection is configured with Sales&Distribuiton?

A. Upon acceptance of the inspection lot.

B. Upon completing the delivery.

C. Upon creating the transfer order.

D. Upon confirming the picking quantities.

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP SD

0 2359
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Integrated Change Control Phase?

Answer

I. Inputs



  • Project management plan

  • Requested changes

  • Work performance information

  • Recommended preventive actions

  • Recommended corrective actions

  • Recommended defect repair

  • Deliverables


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Approved change requests

  • Rejected change requests

  • Project management plan(updates)

  • Project scope statement (updates)

  • Approved corrective actions

  • Approved preventive actions

  • Approved defect repair

  • Validated defect repair

  • Deliverables 

Report Error

View answer Workspace Report Error Discuss

0 2348
Q:

Project Management - Introduction

What is a Project? What are its Characteristics?

Answer

A Project is a temporary endeavour undertaken to create a unique product, service or result.


Characteristics:


1.Temporary 


    Temporary means that every project has a definite beginning and a definite end.


2. Unique Products, Services or Results


   Uniqueness is an important characteristic of project deliverables. For example, many thousands of office buildings have been developed, but each individual facility is unique - different owner, different design, different location, different contractors, and so on.


3. Progressive Elaboration


   Progressive elaboration means developing in steps, and continuing by increments . For example, the project scope will be broadly described early in the project and made more explicit and detailed as the project team develops a better and more complete understanding of the objectives and deliverables.

Report Error