Certification Questions

Q:

 What is the difference between a process and a project?

A) A process is continuous and has no end date, whereas a project has a finite lifespan. B) A project is continuous and has no end date, whereas a process has a finite lifespan.
C) A process stops when the objective has been achieved, whereas a project does not stop when the objective is met. D) In a project the focus is not on the result, whereas with a process the result is important
 
Answer & Explanation Answer: A) A process is continuous and has no end date, whereas a project has a finite lifespan.

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: ITIL Certification

0 5184
Q:

Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction  phase of a project. you are currently in the process of activity sequencing. This is a example of what?

A) Gatekeeping B) Milestone
C) New scope for the project D) Project integration
 
Answer & Explanation Answer: B) Milestone

Explanation:

The approval by the Architecture Review Board is a milestone you want to include in activity sequencing so that you can ensure the requirements for meeting the review board's approval are met.  Answer A is tempting because the question references phase-end activities; however, it is not an example of gatekeeping because the project is not being authorized to continue based only on the architecture review.Gatekeeping often involves the review of other factors as well. Answer C is incorect because the requirement of a review board approval does not afect scope. Answer D is incorrect because project integration planning involves project plan development, execution, and integrated change control, which are not related to a review board.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 5153
Q:

You want to implement a network medium that is not susceptible to EMI. Which type of cabling should you use?

A) Thicknet coax B) Thinnet coax
C) Category 5 UTP cable D) Fiber-optic cable
 
Answer & Explanation Answer: D) Fiber-optic cable

Explanation:

Fiber-optic cable provides a more secure, long - distance cable that is not susceptible to EMI interference at high speeds.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 5138
Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 5125
Q:

What is the purpose of the DHCP server?

A - to provide storage for email
B - to translate URLs to IP addresses
C - to translate IPv4 addresses to MAC addresses
D - to provide an IP configuration information to hosts

Answer

Answer : D


Explanation:The main purpose of the DHCP server is to provide IP configuration parameters to hosts such as the default gateway, domain name, Domain Name System – DNS .

Report Error

View answer Workspace Report Error Discuss

Subject: CCNA

4 5116
Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 5110
Q:

How many parallel currencies are possible and at what level they are assigned?

A. 2 local currencies, company code

B. 3 local currencies, company code

C. 2 local currencies, chart of account

D. 3 local currencies, chart of account

Answer

Answer : B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP FI

20 5099
Q:

You have a computer named Computer1 that runs Windows Vista and a computer named Computer2 that runs Windows 7. You plan to migrate all profiles and user files from Computer1 to Computer2.


You need to identify how much space is required to complete the migration.
What should you do?

A) On Computer1 run Loadstate c:\store /nocompress B) On Computer1 run Scanstate c:\store /nocompress /p
C) On Computer2 run Loadstate \\computer1\store /nocompress D) On Computer2 run Scanstate \\computer1\store /nocompress /p
 
Answer & Explanation Answer: B) On Computer1 run Scanstate c:\store /nocompress /p

Explanation:
Report Error

View Answer Report Error Discuss

8 5014