Certification Questions

Q:

If you want to chose a different set of fields in a vendor account line item display, you choose a different

A. line layout

B. sort variant

C. totals variant

D. additional fields

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP FI

4 4400
Q:

 If an organization is able to become more proactive in its ITSM processes, what is likely to happen to support costs?

A) They are likely to increase gradually B) They are likely to gradually reduce
C) They are likely to increase dramatically D) They are likely to reduce initially and then gradually return to current level
 
Answer & Explanation Answer: B) They are likely to gradually reduce

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: ITIL Certification

1 4397
Q:

You have a reference computer that runs Windows 7.

You plan to deploy an image of the computer.

You create an answer file named answer.xml.

You need to ensure that the installation applies the answer file after you deploy the image. Which command should you run before you capture the image?

A) Imagex.exe /append answer.xml /check B) Imagex.exe /mount answer.xml /verify
C) Sysprep.exe /reboot /audit /unattend:answer.xml D) Sysprep.exe /generalize /oobe /unattend:answer.xml
 
Answer & Explanation Answer: D) Sysprep.exe /generalize /oobe /unattend:answer.xml

Explanation:
Report Error

View Answer Report Error Discuss

5 4385
Q:

You have started your own company based upon PMI methodologies and have been contracted by the government to develope a new interface for one of its computer applications. You develope a solution and win the bid for the contract but encounter problems at the end of the project when the customer says that you did not fullfill their needs. You are throughly shocked. What is your conclusion of the situation?

A) There are always more customers available B) If the customer is not satisfied, the project is not successful
C) Change control management was not effective D) The customer did not communicate very well
 
Answer & Explanation Answer: B) If the customer is not satisfied, the project is not successful

Explanation:

Answer A is incorrect because without satisfied customers, we do not have potential for new projects. Answer C is incorrect because the change control management process would have likely resolved this problem. Answer D is incorrect because it is the project manager's responsibility to seek communication with the customer to set realistic expectations.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4380
Q:

Business area is determined for accounting documents generated automatically from logistics modules are on the basis of

A. plant-division combination

B. plant-sales area combination

C. plant-division-distribution channel combination

D. plant-division combination and sales area

Answer

Answer : D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP FI

3 4376
Q:

What is one way to limit a user's access to only a specific number of accounts in the MCC?

Answer

Create a new MCC account linked to the original MCC account. Move the specified number of accounts into that MCC and grant the user access to the sub-MCC account.

Report Error

View answer Workspace Report Error Discuss

16 4368
Q:

Which command will show you whether a DTE or a DCE cable is plugged into serial 0?

A) sh int s0 B) sh int serial 0
C) show controllers s 0 D) show serial 0 controllers
 
Answer & Explanation Answer: C) show controllers s 0

Explanation:

The Show controllers serial 0 command will show you whether either a DTE or DCE cable is connected to the interface. If it is a DCE connection, you need to add clocking with the clock rate command

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 4361
Q:

At which layer of the OSI model would you assume the problem is if you type show interface serial 1 and receive the following message?

Serial 1 is down, line protocol is down

A) Physical layer B) Data Link layer
C) Network layer D) None
 
Answer & Explanation Answer: A) Physical layer

Explanation:

If you see that a serial interface and the protocol are both down, then you have a physical layer problem. If you see serial 1 is up, line protocol is down, then you are not receiving (Data Link) Keepalives from the remote end.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 4321