Q:

Report Performance is a member of which process group?

A) Controlling B) Planning
C) Executing D) Closing
 
Answer & Explanation Answer: A) Controlling

Explanation:

The processes in the controlling group are Verify Scope, Control Scope, Control Schedule, Control Costs, Perform Quality Control, Report Performance, Monitor and Control Risks, and Administer Procurements.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 2934
Q:

One of the main tasks of asset accounting is to represent the asset portfolio in the detailed form of an asset history sheet.

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

Subject: SAP FI

0 2931
Q:

Partial deliveries are controlled by an indicator thet you set in the:

A. Sold to master record.

B. Delivery schedule line category.

C. Delivery document type.

D. Customer material information record.

Answer

Answer : A , D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP SD

0 2928
Q:

How does DHCP client ensure that no other computer has its assigned IP address?

A) Acknowledge receipt of a TCP segment B) Ping to its own address to see if a response is detected
C) Broadcast a Proxy ARP D) Broadcast a gratuitous ARP
 
Answer & Explanation Answer: D) Broadcast a gratuitous ARP

Explanation:

To stop possible address conflicts , a DHCP client will use gratuitous ARP (broadcast an ARP request for its own IP address) to see if another host responds.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 2927
Q:

Project Risk Management

What are the Project Management Processes included in the Project Risk Management? 

Answer

The Project Risk Management Processes include the following:


Risk Management Planning - Deciding how to approach , plan, and execute the risk management activities for a project


Risk Identification - Determining which risks might affect the project and documenting their characteristics.


Qualitative Risk Analysis - Prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact


Quantitative Risk Analysis - Numerically analyzing the effect on overall project objectives of identified risks


Risk Response Planning - Developing options and actions to enhance opportunities , and to reduce threats to project objectives.


Risk Monitoring and Control - Tracking identified risks, monitoring residual risks, identifying new risks, executing risk response plans, and evaluating their effectiveness throughout the project life cycle.

Report Error

View answer Workspace Report Error Discuss

0 2925
Q:

You want to prevent the creation of administrative shares on a Windows 2000 server computer. What should you do?

A) Nothing. You can't prevent the creation of administrative shares. B) Configure the Advanced options in Configure Your Server
C) Configure the Advanced settings on the View tab in Folder Options D) Use Reged32.exe or the System Policy Editor to edit the registry
 
Answer & Explanation Answer: D) Use Reged32.exe or the System Policy Editor to edit the registry

Explanation:

Edit the registry to prevent the creation of administrative shares.

Report Error

View Answer Report Error Discuss

0 2924
Q:

If there is no gain or loss on the asset retirement, the sales revenue equals to the net book value of the asset.

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

Subject: SAP FI

0 2919
Q:

Monitoring and Controlling Process Group

What are the Project Management Processes included in Monitoring and Controlling Process Group?

Answer


    • Monitor and Control Project Work

    • Integrated Change Control

    • Scope Verification

    • Scope Control

    • Schedule Control

    • Cost Control

    • Perform Quality Control

    • Manage Project Team

    • Performance Reporting

    • Manage Stakeholders

    • Risk Monitoring and Control

    • Contract Administration