Certification Questions

Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop Project Charter phase?

Answer

I. Inputs



  • Contract (when applicable)

  • Project statement of work

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project selection methods

  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs


         1. Project charter

Report Error

View answer Workspace Report Error Discuss

0 1682
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project scope management plan

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Change control system

  • Variance analysis

  • Replanning

  • Configuration management system


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure(updates)

  • WBS dictionary (updates)

  • Scope baseline (updates)

  • Requested changes

  • Recommended  corrective action

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1682
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Quality Planning ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Project management plan


II. Tools and Techniques



  • Cost - benifit analysis

  • Benchmarking

  • Design of experiments

  • Cost of quality(COQ)

  • Additional quality planning tools


III. Outputs



  • Quality management plan

  • Quality metrics 

  • Quality checklists

  • Process improvement plan

  • Quality baseline

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1679
Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Manage stakeholders?

Answer

I. Inputs



  • Communications management plan 

  • Organizational process assets


II. Tools and Techniques



  • Communications methods

  • Issue logs


III. Outputs



  • Resolved issues

  • Approved change requests

  • Approved corrective actions 

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1678
Q:

Project Scope Management

What are the Project Management Processes included in the Project Scope Management?

Answer

Scope Planning - Creating a project scope management plan that documents how the project scope will be defined,verified, controlled, and how the work breakdown structure (WBS) will be created and defined.


Scope Definition - Developing a detailed project scope statement as the basis for future project decisions.


Create WBS - Subdividing the major project deliverables and project work into smaller, more manageable components


Scope Verification - Formalizing acceptance of the completed project deliverables.


Scope Control - Controlling changes to the project scope.

Report Error

View answer Workspace Report Error Discuss

0 1676
Q:

Which tab should you use to change the page orientation of a report?

A. Select the report tab; in Report Manager, select the Properties tab and select the Page Orientation

B. Click File Page Setup and select Page Orientation

C. In InfoView Preferences, change the default page orientation

D. Select the report page; in Report Manager, select the Properties tab and select the Page Orientation

Answer

Answer : D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP BW

0 1673
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Control?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics 

  • Quality checklists

  • Organizational process assets

  • Work performance information

  • Approved change requests

  • Deliverables


II. Tools and Techniques



  • Cause and effect diagram

  • Control charts

  • Flow Charting

  • Histogram

  • Pareto chart

  • Run chart

  • Scatter diagram

  • Statistical sampling

  • Inspection

  • Defect repair review


III. Outputs



  • Quality control measurements

  • Validated defect repair

  • Quality baseline (updates)

  • Recommended corrective actions

  • Recommended preventive actions

  • Requested changes

  • Recommended defect repair

  • Organization process assets (updates)

  • Validated deliverables

  • Project management plan (updates)


 


 

Report Error

View answer Workspace Report Error Discuss

0 1670
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Quantitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Risk management plan

  • Risk register

  • Project management plan


                 - Project schedule management plan


                 - Project cost management plan


II. Tools and Techniques



  • Data gathering and representation techniques

  • Quantitative risk analysis and modeling techniques


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 1670