Certification Questions

Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope Verification ?

Answer

I. Inputs



  • Project scope statement

  • WBS dictionary

  • Project scope management plan

  • Deliverables


II. Tools and Techniques



  • Inspection


III. Outputs



  • Accepted  deliverables

  • Requested changes

  • Recommended corrective actions

Report Error

View answer Workspace Report Error Discuss

0 1652
Q:

[CO-OM-OPA] When creating an overhead cost order, the settlement rule must be entered in the control data. Which settlement receivers are available for internal orders?

A. Asset
B. Cost center
C.Orders
D. General ledger accounts
E. Vendor

Answer

Answer : A , B , C , D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

0 1650
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Assurance?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics

  • Process improvement plan 

  • Work performance information 

  • Approved change requests

  • Quality control measurements 

  • Implemented change requests

  • Implemented corrective actions 

  • Implemented defect repair

  • Implemented preventive actions 


II. Tools and Techniques



  • Quality planning tools and techniques

  • Quality audits

  • Process analysis 

  • Quality control tools and techniques


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1649
Q:

Project Human Resource Management

What are the Project Management Processes included in the Project Human Resource Management?

Answer

Human Resource Planning - Identifying and documenting Project roles, responsibilities, and reporting relationships, as well as creating the staffing management plan.


Acquire Project Team - Obtaining the human resources needed to complete the project


Develop Project Team - Improving the competencies and interaction of team members to enhance project performance.


Manage Project Team - Tracking team member performance, providing feedback, resolving issues, and coordinating changes to enhance project performance.

Report Error

View answer Workspace Report Error Discuss

0 1645
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets 

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary 

  • Project management plan


             - Schedule management plan


             - Staffing management plan


             - Risk register


II. Tools and Techniques



  • Analogous estimating

  • Determine resource cost rates

  • Bottom-up estimating

  • Parametric estimating

  • Project management software

  • Vendor bid analysis

  • Reserve analysis

  • Cost of quality


III. Outputs



  • Activity cost estimates 

  • Activity cost estimate supporting detail 

  • Requested changes

  • Cost management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1639
Q:

You are planning to install and configure network services for ineroperability on your Windows 2000 Server computer. You specifically want this server to maintain and advertise a list of services that use the NWLink IPX/SPX/NetBIOS Compatible Transport Protocol. What service should you install?

A) Indexing Service B) NNTP Service
C) RIP Listener D) SAP Agent
 
Answer & Explanation Answer: D) SAP Agent

Explanation:

The SAP Agent enables a Windows 2000 computer to maintain and advertise a list of servers (such as NetWare servers) that use the NWLink IPX/SPX/NetBIOS Compatible Transport Protocol.

Report Error

View Answer Report Error Discuss

0 1634
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop project management plan phase?

Answer

I. Inputs



  • Preliminary project scope statement

  • Project management processes

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Project management plan

Report Error

View answer Workspace Report Error Discuss

0 1632
Q:

You would like to use the command line to end an application that a Terminal Services client is running. What command can you use?

A) Tscon B) Tsprof
C) Tsend D) Tskill
 
Answer & Explanation Answer: D) Tskill

Explanation:

Tskill ends a process. Since you want to stop an application, this is the command you would use.

Report Error

View Answer Report Error Discuss

0 1632