Certification Questions

Q:

4 phases of project management are

Answer

The project management life cycle describes high-level processes for delivering a successful project.


The project management life cycle is usually broken down into four phases:


1. Initiation and Planning,


2. Execution,


3. Project Monitoring and Control, and


4. Project Closing.

Report Error

View answer Workspace Report Error Discuss

4 1614
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Monitoring and Control?

Answer

I. Inputs



  • Risk management plan

  • Risk register

  • Approved change requests

  • work performance information

  • performance reports


II. Tools and Techniques



  • Risk reassessment

  • Risk audits

  • Variance and trend analysis

  • Technical performance measurement

  • Reserve analysis

  • Status meetings


III. Outputs



  • Risk register (updates)

  • Requested changes

  • Recommended corrective actions

  • Recommended preventive actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1613
Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Communications planning?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Project management plan


                   - Constraints


                   - Assumptions


II. Tools and Techniques



  • Communications requirements analysis

  • Communications technology


III. Outputs



  • Communications management plan

Report Error

View answer Workspace Report Error Discuss

0 1607
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Sequencing ?

Answer

I.Inputs



  • Project scope statement

  • Activity list

  • Activity attributes

  • Milestone list

  • Approved change requests


II. Tools and Techniques



  • Precedence Diagramming Method (PDM)

  • Arrow Diagramming Method (ADM)

  • Schedule network templates 

  • Dependency determination

  • Applying leads and lags 


III. Outputs



  • Project schedule network diagrams

  • Activity list (updates)

  • Activity attributes (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 1606
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Activity resource requirements

  • Resource calendars

  • Project management plan


               - Risk register


               - Activity cost estimates


II. Tools and Techniques



  • Expert judgment

  • Analogous  estimating

  • Parametric estimating

  • Three-point estimates 

  • Reserve analysis


III. Outputs



  • Activity duration estimates

  • Activity attributes (updates)

Report Error

View answer Workspace Report Error Discuss

0 1603
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Monitor and Control Project Work phase?

Answer

I. Inputs



  • Project management plan

  • Work performance information

  • Rejected Change requests


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Earned value technique

  • Expert Judgment


III. Outputs



  • Recommended corrective actions

  • Recommended preventive actions

  • Forecasts

  • Recommended defect repair

  • Requested changes 

Report Error

View answer Workspace Report Error Discuss

1 1601
Q:

What should you use Ad Groups for?

Answer

To organize ads by common themes that you want to advertise on.

Report Error

View answer Workspace Report Error Discuss

0 1600
Q:

[CO-OM-CCA] Assessment is designed for what?

A. It classifies the specific activities provided y a cost center along cost allocation lines.

B. Allocation of primary and secondary costs from a sender to receiver controlling objects.

C. Allocation of amounts within CO across company codes.

D. Activating plan integration with Orders and projects.

Answer

Answer : B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO