Questions

Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop Project Charter phase?

Answer

I. Inputs



  • Contract (when applicable)

  • Project statement of work

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project selection methods

  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs


         1. Project charter

Report Error

View answer Workspace Report Error Discuss

0 2099
Q:

What year was the first Oscar Awards ceremony held?

A) 1945 B) 1929
C) 1931 D) 1954
 
Answer & Explanation Answer: B) 1929

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Honours and Awards
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

4 2098
Q:

Which action is an example of direct democracy?

A) voting for the recall of a state governor B) serving as an official in the local government
C) protesting unfavorable government legislation D) electing a member to the state senate
 
Answer & Explanation Answer: A) voting for the recall of a state governor

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Politics
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

1 2098
Q:

The ozone layer is part of the

A) Troposphere B) Stratosphere
C) Ionosphere D) Mesosphere
 
Answer & Explanation Answer: B) Stratosphere

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

2 2098
Q:

Improve the bracketed part of the sentence.
We (are looking forward for) a positive response from you.

A) are looking forward to B) have been looking forward at
C) should look forward at D) No improvement
 
Answer & Explanation Answer: A) are looking forward to

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2098
Q:

In which of the following state its first mega food park was inaugurated?

A) Karnataka B) Telangana
C) Gujarat D) Punjab
 
Answer & Explanation Answer: C) Gujarat

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2097
Q:

Which Police Commissioner launches MobileApp Digicop?

A) Hyderabad B) Chennai
C) Kolkata D) Lucknow
 
Answer & Explanation Answer: B) Chennai

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2097
Q:

Project Management Process Groups

What are the Project Management Process Groups?

Answer

This section identifies and describes the five Project Management Process Groups required for any project. These five process Groups have clear dependencies and are performed in the same sequence on each project.


The five Process Groups are :


Initiating  Process Group - Defines and authorizes the project or a project phase


Planning Process Group - Defines and refines objectives, and plans the course of action required to attain the objectives and scope that the project was undertaken to address.


Executing Process Group - Integrates people and other resources to carry out the project management plan for the project


Monitoring and Controlling process Group - Regularly measures and monitors progress to identify variances from the project management plan so that corrective action can be taken when necessary to meet project objectives.


Closing Process Group - Formalizes acceptance of the product, service or result and brings the project or a project phase to an orderly end.

Report Error

View answer Workspace Report Error Discuss

0 2097