Q:

Project Integration Management

What are the Project Management Processes included in the Project Integration Management?

Answer

The Integrative Project Management Processes include:


Develop Project Charter - Developing the project charter that formally authorizes a project or a project Phase.


Develope Preliminary Project Scope Statement - Developing the preliminary project scope statement that provides a high level scope narrative


Develop Project Management Plan -  Documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans into a project management plan.


Direct and Manage Project Execution- Executing the work defined in the project management plan to achieve the project's requirements defined in the project scope statement.


Monitor and Control Project Work - Monitoring and controlling the processes used to initiate, plan, execute, and close a project to meet the performance objectives defined in the project management plan.


Integrated Change Control - Reviewing all change requests, approving changes, and controlling changes to the deliverables and organizational process assets.


Close Project - Finalizing all activities across all of the Project Management Process Groups to formally close the project or a Project phase.

Report Error

View answer Workspace Report Error Discuss

0 3219
Q:

Which of the following year is considered as the first year of the Muslim calender ? 

A) AD 622 B) AD 671
C) AD 571 D) AD 651
 
Answer & Explanation Answer: A) AD 622

Explanation:

Muhammad had to leave Mecca his birth place where he started preaching and take refuse in Medina, where he was given a warm welcome. This event took place in AD 622 and is known as the year of the Hijira, or migration, which became the first year of the Muslim Calendar.

Report Error

View Answer Report Error Discuss

Filed Under: World History

3 3219
Q:

The atoms of the elements which have same number of neutrons are called

A) Isobars B) Isotopes
C) Isotones D) None
 
Answer & Explanation Answer: C) Isotones

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Chemistry

4 3219
Q:

What kind of fermented juice, made of spirits, sugar and hot water takes its name from the Hindustani word palm tree?

Answer

Toddy

Report Error

View answer Workspace Report Error Discuss

2 3218
Q:

Verify Scope is the process of

A) progressively elaborating and documenting the project work that produces the product of the project. B) subdividing the major product deliverables into smaller, more manageable components.
C) obtaining formal acceptance of the project scope by the stakeholders. D) influencing the factors that create scope changes to ensure that changes are agreed upon, determining that a scope change has occurred and managing the changes when and if they occur.
 
Answer & Explanation Answer: C) obtaining formal acceptance of the project scope by the stakeholders.

Explanation:

“Verify Scope is the process of formalizing acceptance of the completed project deliverables. Verifying scope includes reviewing deliverables with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables by the customer or sponsor.” PMBOK [5.4]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 3218
Q:

Which one of the following actors was awarded the Dada Saheb Phalke Award at the 59th National Film Festival

A) Soumitra Chatterjee B) Ketan Mehta
C) Shekhar Kapoor D) Mahesh Bhatt
 
Answer & Explanation Answer: A) Soumitra Chatterjee

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Honours and Awards

1 3217
Q:

In which Olympics India has won the most number of medals?

A) Rio Olympics 2016 B) Beijing Olympics 2008
C) London Olympics 2012 D) Athens Olympics 2004
 
Answer & Explanation Answer: C) London Olympics 2012

Explanation:

Upto now, India has won 28 medals in Olympics from 1896 - 2016. In that

 

Rio Olympics 2016  - 02

Beijing Olympics 2008 - 03

London Olympics 2012 - 06

Athens Olympics 2004 - 01

 

Hence, India has won most number of medals in 2012 Rio Olympics.

Report Error

View Answer Report Error Discuss

Filed Under: Sports
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 3217
Q:

Where is a hub specified in the OSI model?

A) Physical Layer B) Data Link Layer
C) Application Layer D) Session Layer
 
Answer & Explanation Answer: A) Physical Layer

Explanation:

Hubs regenerate electrical signals, which are specified at the Physical layer.

Report Error

View Answer Report Error Discuss

Filed Under: Networking
Exam Prep: CAT
Job Role: Analyst , Network Engineer

1 3217