PMP Certification Questions

Q:

Project Management Processes

What is the underlying concept for the interaction among the project management processes?

Answer

Plan-do-check-act cycle

Report Error

View answer Workspace Report Error Discuss

0 2347
Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Information Distribution?

Answer

I. Inputs



  • Communications management plan


II. Tools and Techniques



  • Communications skills 

  • Information gathering and retrieval systems

  • Information distribution methods

  • Lessons learned process


III. Outputs



  • Organizational process assets (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2334
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Response Planning?

Answer

I. Inputs



  • Risk management plan

  • Risk register


II. Tools and Techniques



  • Strategies for negative risk or threats

  • Strategies for positive risks or opportunities

  • Strategies for both threats and opportunities

  • Contingent response strategy


III. Outputs



  • Risk register (updates)

  • Project management plan (updates)

  • Risk - related contractual agreements

Report Error

View answer Workspace Report Error Discuss

0 2323
Q:

Project Stakeholders

What do you meant by project stakeholders?

Answer

Project Stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.


Stakeholders may have a positive or negative.


Positive stakeholders are those who would normally benefit from a successful outcome from the project, while negative stakeholders are those who see negative outcomes from the project's success.

Report Error

View answer Workspace Report Error Discuss

0 2307
Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Request Seller Responses?

Answer

I. Inputs



  • Organizational process assets

  • Procurement management plan

  • Procurement documents


II. Tools and Techniques



  • Bidder conferences

  • Advertising

  • Develop qualified sellers list


III. Outputs



  • Qualified sellers list

  • Procurement document package

  • Proposals

Report Error

View answer Workspace Report Error Discuss

0 2256
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Management Planning?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project Scope statement

  • Project Management plan


II. Tools and Techniques



  • Planning meetings and analysis


III. Outputs



  • Risk Management Plan

Report Error

View answer Workspace Report Error Discuss

0 2244
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Quantitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Risk management plan

  • Risk register

  • Project management plan


                 - Project schedule management plan


                 - Project cost management plan


II. Tools and Techniques



  • Data gathering and representation techniques

  • Quantitative risk analysis and modeling techniques


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 2239
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Quality Planning ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Project management plan


II. Tools and Techniques



  • Cost - benifit analysis

  • Benchmarking

  • Design of experiments

  • Cost of quality(COQ)

  • Additional quality planning tools


III. Outputs



  • Quality management plan

  • Quality metrics 

  • Quality checklists

  • Process improvement plan

  • Quality baseline

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2233