Q:
      
      
         
            
The triple constraints of Project Management are frequently discussed in other contextx such as marketing classes and a variety of other subjects. The interaction between _____, ______, and _______can be seen as a triangle, with the three sides impacting the others.
         
       
      
      
      
          
      
      
          Answer & Explanation
         Answer: D) time, scope, cost         
         
Explanation: Scope, quality, and cost are the triple constraints. Quality is a function of these three areas and can impact them; however it is not considered one of the components of the triple constraint. Therefore, Answer A, B, and C are incorect.
       
      
      
      