Q:

We must settle all line items at once, and you do not have to distribute100 percent of each line item for AUC using line item settlement.

A) TRUE B) FALSE
Answer & Explanation Answer: B) FALSE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

Subject: SAP FI

0 4238
Q:

The three tier in R/3 system is represented by

A. user, data base, programs

B. application, data base and customer of R/3

C. presentation client, R/3 application and data base

D. data, user and application

Answer

Answer : C

Report Error

View answer Workspace Report Error Discuss

Subject: SAP FI

4 4215
Q:

Which of the following statements about VPRS(cost) are correct?

A. It is controled by the customer master

B. A condition type VPRS is a statistical condition type

C. A condition record can be created for a condition type VPRS (cost)

D. It is controled by the material master

Answer

Answer : B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP SD

2 4163
Q:

Maximum number of sessions a user can open when he logs on to SAP

A.Six

B.One

C.Three

D.Five

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP FI

1 4115
Q:

Types of depreciation in Asset accounting.Choose the following?

A.Special depreciation            B.Unplanned depreciation

C.Manual depreciation           D.Automatic depreciation

Answer

Answer : A , B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP FI

0 4017
Q:

We can use schedule manager in FI-AA to define, schedule,process and control periodically recurring processes.

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

Subject: SAP FI

0 3973
Q:

Where is a Web Intelligence variable stored?

A. In the document

B. In the Central Management Server (CMS)

C. In the Metadata Cube

D. In the cell

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP BW

2 3892
Q:

The system does a forward scheduling if...

A. Material availability date falls ater today's date

B. If backward scheduling is configured

C. Material availability date falls beyond today's date

D. If backward scheduling is not configured

Answer

Answer : C , D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP SD

0 3791