Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets 

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary 

  • Project management plan


             - Schedule management plan


             - Staffing management plan


             - Risk register


II. Tools and Techniques



  • Analogous estimating

  • Determine resource cost rates

  • Bottom-up estimating

  • Parametric estimating

  • Project management software

  • Vendor bid analysis

  • Reserve analysis

  • Cost of quality


III. Outputs



  • Activity cost estimates 

  • Activity cost estimate supporting detail 

  • Requested changes

  • Cost management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2062
Q:

The outer protein coat of a virus is called a

A) Capsid B) Virion
C) Envelope D) None of the above
 
Answer & Explanation Answer: A) Capsid

Explanation:

The outer protein protective coat of a virus is called a Capsid.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

5 2062
Q:

The criminal was __________ lest he should escape.

A) fetid B) fettered
C) fettled D) feted
 
Answer & Explanation Answer: B) fettered

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English

1 2062
Q:

Net exports are negative when

A) exports are greater than imports B) imports are greater than exports
C) No exports D) None of the above
 
Answer & Explanation Answer: B) imports are greater than exports

Explanation:


When exports are greater than imports, net exports are positive and similarly, when imports are greater than exports, net exports are negative.

 

When a country imports goods, it buys them from foreign producers. The money spent on imports leaves the economy, and that decreases the importing nation's GDP.

Report Error

View Answer Report Error Discuss

Filed Under: Indian Economy
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2062
Q:

Which of the following is a manipuri version of Hockey?

A) Yubi Lakpi B) Khong Kangjei
C) Hiyang Tanaba D) None of the above
 
Answer & Explanation Answer: B) Khong Kangjei

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Geography
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

1 2061
Q:

Select the antonym of
mishmash

A) potpourri B) medley
C) organized D) haphazard
 
Answer & Explanation Answer: C) organized

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2061
Q:

Which tribe of Arunachal Pradesh is celebrating Boori Boot Yollo Festival?

A) Gond B) Bhil
C) Santhals D) Nyishi
 
Answer & Explanation Answer: D) Nyishi

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Culture
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

11 2060
Q:

Project Time Management

What are the Project Management Processes included in the Project Time Management?

Answer

Activity Definition - Identifying the Specific schedule activities that need to be performed to produce the various project deliverables.


Activity Sequencing - Identifying and documenting dependencies among schedule activities


Activity Resource Estimating - Estimating the type and quantities of resources required to perform each schedule activity


Activity Duration Estimating - Estimating the number of work periods that will be needed to complete individual schedule activities


Schedule Development - Analyzing activity sequences, durations, resource requirements, and schedule constraints to creae the project schedule.


Schedule Control - Controlling changes to the project schedule

Report Error

View answer Workspace Report Error Discuss

0 2060