A situation, where several processes access and manipulate the same data concurrently and the outcome of the execution depends on the particular order in which the access takes place, is called race condition. To guard against the race condition we need to ensure that only one process at a time can be manipulating the same data. The technique we use for this is called process synchronization.

Report Error

View answer Workspace Report Error Discuss

1 2063
Q:

Project Time Management

What are the Project Management Processes included in the Project Time Management?

Answer

Activity Definition - Identifying the Specific schedule activities that need to be performed to produce the various project deliverables.


Activity Sequencing - Identifying and documenting dependencies among schedule activities


Activity Resource Estimating - Estimating the type and quantities of resources required to perform each schedule activity


Activity Duration Estimating - Estimating the number of work periods that will be needed to complete individual schedule activities


Schedule Development - Analyzing activity sequences, durations, resource requirements, and schedule constraints to creae the project schedule.


Schedule Control - Controlling changes to the project schedule

Report Error

View answer Workspace Report Error Discuss

0 2062
Q:

The criminal was __________ lest he should escape.

A) fetid B) fettered
C) fettled D) feted
 
Answer & Explanation Answer: B) fettered

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English

1 2062
Q:

Innate immune system defenses include

A) phagocytosis B) B cells
C) plasma cells D) T cells
 
Answer & Explanation Answer: A) phagocytosis

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

1 2062
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Create WBS ?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Project scope management  plan

  • Approved Change requests


II. Tools and Techniques



  • Work breakdown structure templates

  • Decomposition


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure

  • WBS dictionary

  • Scope baseline

  • Project scope management plan(updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2060
Q:

The swift movement of the falling water droplets along with the rising air create lightning and sound. It is this event that we call a ________________.

A) thunderstorm B) hail
C) twister D) cloudburst
 
Answer & Explanation Answer: A) thunderstorm

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: Bank Exams

3 2060
Q:

Upanishads are the ______________________

A) Great Epics B) Story Books
C) Source of Hindu Philosophy D) Law Books
 
Answer & Explanation Answer: C) Source of Hindu Philosophy

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

3 2060
Q:

The idea of cache memory is based on___.

A) on the heuristic 90-10 rule B) on the property of locality of reference
C) on the fact that references generally tend to cluster D) All options are correct
 
Answer & Explanation Answer: B) on the property of locality of reference

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Computer
Exam Prep: Bank Exams

14 2059