Questions

Q:

Which of the following pair is INCORRECT?
I. Parsec - Distance
II. Barrel - Liquid
III. Light year - Time

A) Only III B) Only I and III
C) Only II D) All are correct
 
Answer & Explanation Answer: A) Only III

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: Bank Exams

3 2070
Q:

Upanishads are the ______________________

A) Great Epics B) Story Books
C) Source of Hindu Philosophy D) Law Books
 
Answer & Explanation Answer: C) Source of Hindu Philosophy

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

3 2070
Q:

In the following question, out of the given four alternatives, select the one which is opposite in meaning of the given word.

Vagrant

A) Idle B) Roving
C) Settled D) Wanderer
 
Answer & Explanation Answer: C) Settled

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2070
Q:

What was the former name of Ho Chi Minh city?

Answer

Saigon

Report Error

View answer Workspace Report Error Discuss

Subject: World Geography

0 2070
Q:

In Geography, who propounded the theory of convectional current Hypothesis?

A) Carl Ritter B) Immanuel Kant
C) Arthur Holmes D) Arnaldo Faustini
 
Answer & Explanation Answer: C) Arthur Holmes

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Geography
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2070
Q:

The First battle of which war was the Battle of Alma?

A) Creek war B) Crimean war
C) Korean war D) Chinese war
 
Answer & Explanation Answer: B) Crimean war

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World History

2 2069
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop project management plan phase?

Answer

I. Inputs



  • Preliminary project scope statement

  • Project management processes

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Project management plan

Report Error

View answer Workspace Report Error Discuss

0 2069
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Budgeting ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Activity cost estimates

  • Activity cost estimate supporting detail

  • Project schedule 

  • Resource calendars 

  • Contract

  • Cost management plan


II. Tools and Techniques



  • Cost aggregation

  • Reserve analysis

  • Parametric estimating 

  • Funding limit reconciliation


III. Outputs



  • Cost baseline 

  • Project funding requirements 

  • Cost management plan (updates)

  • Requested changes

Report Error