Q:
Three men, four women and six children can complete a work in 9 days. A women does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 9 days?
Answer & Explanation
Answer: A) 7
Explanation: Given (3 Men + 4 Women + 6 Children) -----> 9 days
But W = 2M and C = M/2
Now, convert Men and Children into Women by
Therefore, 7 women alone can complete this work in 9 days.