Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Budgeting ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Activity cost estimates

  • Activity cost estimate supporting detail

  • Project schedule 

  • Resource calendars 

  • Contract

  • Cost management plan


II. Tools and Techniques



  • Cost aggregation

  • Reserve analysis

  • Parametric estimating 

  • Funding limit reconciliation


III. Outputs



  • Cost baseline 

  • Project funding requirements 

  • Cost management plan (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2087
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Resource Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Activity list

  • Activity attributes

  • Resource availability

  • Project management plan


II. Tools and Techniques



  • Expert Judgment

  • Alternatives analysis

  • Published estimating data

  • Project management software

  • Bottom-up estimating


III. Outputs



  • Activity resource requirements

  • Activity atributes (updates)

  • Resource breakdown structure

  • Resource calendars (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2086
Q:

The purpose of defibrillation is to

A) prevent asystole from deteriorating into ventricular fibrillation B) stop the chaotic, disorganized contraction of the cardiac cells
C) cause a rapid decrease in the heart rate of an unstable patient D) improve the chance of cardiopulmonary resuscitation (CPR) being successful in resuscitation
 
Answer & Explanation Answer: B) stop the chaotic, disorganized contraction of the cardiac cells

Explanation:

The purpose of defibrillation is to stop the chaotic, disorganized contraction of the cardiac cells. Defibrillation is a technique used in emergency medicine to terminate ventricular fibrillation or pulseless ventricular tachycardia. It uses an electrical shock to reset the electrical state of the heart so that it may beat to a rhythm controlled by its own natural pacemaker cells.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

1 2086
Q:

Most stars are at what point in their life cycles?

A) Supernova B) Protostar
C) Red Giant D) Main Sequence
 
Answer & Explanation Answer: D) Main Sequence

Explanation:

most_stars_are_at_what_point_in_their_life_cycles1560330646.jpg image

Most stars are at main sequence point in their life cycles.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2086
Q:

Collisions occur at curves because

A) speed on the approach is too great B) speed leaving the curve is not enough
C) speed leaving the curve is too great D) speed on the approach is not enough
 
Answer & Explanation Answer: A) speed on the approach is too great

Explanation:

Collisions occur at curves because speed on the approach is too great.

Collisions_occur_at_curves_because1560944223.jpg image

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

1 2085
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop project management plan phase?

Answer

I. Inputs



  • Preliminary project scope statement

  • Project management processes

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Project management plan

Report Error

View answer Workspace Report Error Discuss

0 2085
Q:

Which Governor General abolished the 'Sati System' in India?

A) Lord Canning B) Lord Ripon
C) Lord Wiliam Bentinck D) Lord Dalhousie
 
Answer & Explanation Answer: C) Lord Wiliam Bentinck

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History
Exam Prep: Bank Exams

3 2085