Questions

Q:

Which is the longest National Highway in India?

A) NH - 47 B) NH - 4
C) NH - 7 D) NH - 44
 
Answer & Explanation Answer: D) NH - 44

Explanation:

NH - 44 covering Srinagar to Kanyakumari is the longest National Highway in India by the NHDP. It covers a distance of 3,745 Kms. It was previously known as NH - 7.

Report Error

View Answer Report Error Discuss

Filed Under: Indian Geography
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

1 2944
Q:

Which poet first popularized the sonnet form?

A) Edmund Spencer B) Francesco Petrarch
C) Shakespeare D) None of the above
 
Answer & Explanation Answer: B) Francesco Petrarch

Explanation:

The sonnet is a fourteen-line poem written in iambic pentameter, which employ one of several rhyme schemes and adhere to a tightly structured thematic organization. Francesco Petrarch first popularized the sonnet form and after that many others like Shakespeare, Edmund Spencer and many other started that.

Report Error

View Answer Report Error Discuss

Filed Under: Indian History
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2944
Q:

Who of the following is not a recepient of 2011 Nobel Peace prize

A) Hu Jintao B) Leymah Gbowee
C) Ellen Johnson Sirleaf D) Tawakkol Karman
 
Answer & Explanation Answer: A) Hu Jintao

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Honours and Awards

0 2944
Q:

Which of the following decade is celebrated as United Nations Decade for Women

A) 1997-2006 B) 2001-2010
C) 1976-1985 D) 2003-2012
 
Answer & Explanation Answer: C) 1976-1985

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Honours and Awards

0 2943
Q:

What is the biggest island in the Caribbean?

Answer

Cuba

Report Error

View answer Workspace Report Error Discuss

Subject: World Geography

1 2943
Q:

Report Performance is a member of which process group?

A) Controlling B) Planning
C) Executing D) Closing
 
Answer & Explanation Answer: A) Controlling

Explanation:

The processes in the controlling group are Verify Scope, Control Scope, Control Schedule, Control Costs, Perform Quality Control, Report Performance, Monitor and Control Risks, and Administer Procurements.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 2943
Q:

Project Risk Management

What are the Project Management Processes included in the Project Risk Management? 

Answer

The Project Risk Management Processes include the following:


Risk Management Planning - Deciding how to approach , plan, and execute the risk management activities for a project


Risk Identification - Determining which risks might affect the project and documenting their characteristics.


Qualitative Risk Analysis - Prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact


Quantitative Risk Analysis - Numerically analyzing the effect on overall project objectives of identified risks


Risk Response Planning - Developing options and actions to enhance opportunities , and to reduce threats to project objectives.


Risk Monitoring and Control - Tracking identified risks, monitoring residual risks, identifying new risks, executing risk response plans, and evaluating their effectiveness throughout the project life cycle.

Report Error

View answer Workspace Report Error Discuss

0 2943
Q:

Have you studied buses? What types?

Answer

There are three types of buses.


Address bus: This is used to carry the Address to the memory to fetch either Instruction or Data.


Data bus: This is used to carry the Data from the memory.


Control bus: This is used to carry the Control signals like RD/WR, Select etc.

Report Error

View answer Workspace Report Error Discuss

Subject: Hardware

0 2943