Questions

Q:

Who was sworn in as the 44th Chief Justice of India (CJI) recently ?

A) Justice Tirath Singh Thakur B) Justice Atul Mehta
C) Justice Jagdish Singh Khehar D) Justice T M Goyal
 
Answer & Explanation Answer: C) Justice Jagdish Singh Khehar

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Famous Personalities
Exam Prep: Bank Exams , CAT
Job Role: Bank Clerk , Bank PO

6 3836
Q:

The main goal for farmers in 1900 was to

A) Force the railroads to lower freight rates B) Enable them to pay back their loans more easily
C) Hold on to political and economic power. D) voters greater direct participation in government
 
Answer & Explanation Answer: C) Hold on to political and economic power.

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

3 3836
Q:

Application layer protocol defines

A) message format, syntax and semantics B) rules for when and how processes send and respond to messages
C) types of messages exchanged D) All of the above
 
Answer & Explanation Answer: D) All of the above

Explanation:

Application layer protocol defines types of messages exchanged, message format, syntax and semantics and rules for when and how processes send and respond to messages.

Report Error

View Answer Report Error Discuss

Filed Under: Networking
Exam Prep: AIEEE
Job Role: Network Engineer

4 3835
Q:

Which of the following properties is found only in ferromagnetic materials ?

A) Susceptibility independent of temperature B) Point in a particular direction
C) Hysteresis D) Attracting a magnetic substance
 
Answer & Explanation Answer: C) Hysteresis

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE , Bank Exams

3 3835
Q:

An important tool for project scope management is

A) Fast tracking B) Work breakdown structure
C) Crashing D) A Gantt Chart
 
Answer & Explanation Answer: B) Work breakdown structure

Explanation:

Work breakdown structure is an important tool for project scope management.

 

Project Scope Management refers to the set of processes that ensure a project’s scope is accurately defined and mapped. Scope Management techniques enable project managers and supervisors to allocate just the right amount of work necessary to successfully complete a project—concerned primarily with controlling what is and what is not part of the project’s scope.

Report Error

View Answer Report Error Discuss

8 3834
Q:

By the Act of 1858, the powers of the Board of Control and the Court of Directors were transferred to ........

A) The Secretary of State B) Parliament
C) Viceroy D) Commander- in - Chief
 
Answer & Explanation Answer: A) The Secretary of State

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History

3 3834
Q:

When is the shortest day observed?

A) June 21 B) December 22
C) June 22 D) December 21
 
Answer & Explanation Answer: B) December 22

Explanation:

Shortest of all the days is observed on Decenber 22

Report Error

View Answer Report Error Discuss

11 3834
Q:

For the oxidation, carbohydrates should be in the form of

A) Starch B) Cellulose
C) Glucose D) Fats
 
Answer & Explanation Answer: C) Glucose

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Biology

3 3834