Project Time Management

What are the Project Management Processes included in the Project Time Management?

Answer

Activity Definition - Identifying the Specific schedule activities that need to be performed to produce the various project deliverables.


Activity Sequencing - Identifying and documenting dependencies among schedule activities


Activity Resource Estimating - Estimating the type and quantities of resources required to perform each schedule activity


Activity Duration Estimating - Estimating the number of work periods that will be needed to complete individual schedule activities


Schedule Development - Analyzing activity sequences, durations, resource requirements, and schedule constraints to creae the project schedule.


Schedule Control - Controlling changes to the project schedule

Report Error

View answer Workspace Report Error Discuss

0 2075
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets 

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary 

  • Project management plan


             - Schedule management plan


             - Staffing management plan


             - Risk register


II. Tools and Techniques



  • Analogous estimating

  • Determine resource cost rates

  • Bottom-up estimating

  • Parametric estimating

  • Project management software

  • Vendor bid analysis

  • Reserve analysis

  • Cost of quality


III. Outputs



  • Activity cost estimates 

  • Activity cost estimate supporting detail 

  • Requested changes

  • Cost management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2075
Q:

The First battle of which war was the Battle of Alma?

A) Creek war B) Crimean war
C) Korean war D) Chinese war
 
Answer & Explanation Answer: B) Crimean war

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World History

2 2074
Q:

What's the maximum hard drive size for FAT16-based Windows system?

Answer

Maximum hard drive size for FAT16-based windows system is 2GB.

Report Error

View answer Workspace Report Error Discuss

Subject: Hardware

0 2074
Q:

Agronomy is a branch of agriculture that deals with

A) Study of crops B) Study of soil
C) Both A & B D) None of the above
 
Answer & Explanation Answer: C) Both A & B

Explanation:

Agronomy is a branch of agriculture that deals with the study of crops and the soils in which they are produced.

Report Error

View Answer Report Error Discuss

Filed Under: Indian Geography
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2074
Q:

Administered prices refer to

Answer

Administered prices are prices set by government or firms which are not determined by regular market forces. They do not vary in response to short-run fluctuations in demand and supply conditions.


Examples include price controls and rent controls.

Report Error

View answer Workspace Report Error Discuss

Subject: Indian Economy Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

0 2073
Q:

Where's MBR located on the disk?

Answer

Main Boot Record is located is sector 0, track 0, head 0, cylinder 0 of the primary active partition.

Report Error

View answer Workspace Report Error Discuss

Subject: Hardware

0 2073
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Create WBS ?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Project scope management  plan

  • Approved Change requests


II. Tools and Techniques



  • Work breakdown structure templates

  • Decomposition


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure

  • WBS dictionary

  • Scope baseline

  • Project scope management plan(updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2073