Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 5278
Q:

The book " Truth, love and A Little Malice " is written by 

A) Tarun Tejpal B) Vikram Seth
C) Khushwant Singh D) Nirad C. Chaudhuri
 
Answer & Explanation Answer: C) Khushwant Singh

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Books and Authors

8 5276
Q:

Parasec is ythe unit of

A) distance B) time
C) intensity of light D) magnetic line
 
Answer & Explanation Answer: A) distance

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics

3 5276
Q:

______ is the first state to have Logo for Vehicles Driven by person with Hearing Impairment ?

A) Telangana B) Rajasthan
C) Gujarat D) Haryana
 
Answer & Explanation Answer: A) Telangana

Explanation:

Telangana has introduced a logo for identifying vehicles driven by persons with hearing impairment and has become the first state in the country to do so. 

The logo was designed by city-based graphic designer Manikanta Annapragada who was the first person to obtain a driving licence under the ‘hearing impaired’ category in the country.

The logo consists of a hearing impaired mark along with text saying, “Driver is deaf — Please watch out”.

Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Bank Clerk

5 5274
Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 5274
Q:

Which is the folk dance of Andhra Pradesh?

A) Kolattam B) Karakattam
C) Lavani D) Saturi
 
Answer & Explanation Answer: A) Kolattam

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Culture

62 5273
Q:

'The Peloponnesian war' was fought between _______ and _____

A) Sparta and Iran B) Sparta and Athens
C) Athens and Iran D) Athens and Asia Minor
 
Answer & Explanation Answer: B) Sparta and Athens

Explanation:

The Peloponnesian war, between Athens and Sparta from 431 to 404 BC ended in the defeat of Athens and the destruction of her democracy. Athens became a subject state of sparta. This war marked the beginning of the end of the "Glory that was Greece".

Report Error

View Answer Report Error Discuss

Filed Under: World History

9 5271
Q:

Which is the World's highest bridge standing 1850 ft above a gorge opens?

A) Sidu Bridge B) Millau Via-duct
C) Beipanjiang Bridge D) Puli Bridge
 
Answer & Explanation Answer: C) Beipanjiang Bridge

Explanation:

Duge Beipanjiang Bridge in southwest China, opened to traffic this week and now the highest bridge in the world, some 565 metres (1,854 feet) above the valley below.The bridge stretches across a 1,341-metre (4,400-foot) span. Three years in the making, it's estimated to have cost the Chinese government around 1 billion yuan (or US$144 million).The bridge is going to cut travel times between Liupanshui in the Guizhou province and Xuanwei in the Yunnan province to two hours instead of the current five – as long as you don't mind the heights.The bridge crosses the the Nizhu river, and to give you some idea of the size of the drop down to the water below, it's almost 2 Eiffel Towers or one-and-a-half Empire State Buildings.

Report Error

View Answer Report Error Discuss

Filed Under: Longest, Shortest, Deepest
Exam Prep: Bank Exams , CAT , GATE , GRE
Job Role: Bank Clerk , Bank PO , Network Engineer

11 5270