Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Close project Phase?

Answer

I. Inputs



  • Project management plan

  • Contract documentation

  • Enterprise environmental factors

  • Organizational process assets

  • Work performance information

  • Deliverables


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Administrative closure procedure

  • Contract closure procedure

  • Final product, service, or result

  • Organisational process assets (updates)

Report Error

View answer Workspace Report Error Discuss

0 2364
Q:

Project Procurement Management

What are the Project Management Processes included in the Project Procurement Management?

Answer

The Project Procurement Management processes include the following:


Plan Purchases and Acquisitions - determining what to purchase or acquire and determining when and how.


Plan Contracting - documenting products, services, and results requirements and identifying potential sellers.


Request Seller Responses - obtaining information, quotations, bids, offers, or proposals, as appropriate.


Select Sellers - reviewing offers, choosing among potential sellers, and negotiating a written contract with each seller.


Contract Administration - managing the contract and relationship between the buyer and seller , reviewing and documenting how a seller is performing or has performed to establish required corrective actions and provide a basis for future relationships with the seller, managing contract-related changes and, when appropriate , managing the contractual relationship with the outside  buyer of the project.


Contract Closure - completing and settling each contract, including the resolution of any open items, and closing each contract applicable to the project or a project phase 

Report Error

View answer Workspace Report Error Discuss

0 2363
Q:

Who started Shudhi Movement?

A) Dayananda Saraswathy B) Sri Aurobindo
C) Swami Vivekananda D) Yashoda Bhai
 
Answer & Explanation Answer: A) Dayananda Saraswathy

Explanation:

Shudhi Movement was started by Dayananda Saraswathy.

Report Error

View Answer Report Error Discuss

Filed Under: Indian History
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

3 2363
Q:

when an atom loses an electron it becomes

A) neutron B) negative ion
C) positive ion D) none of the above
 
Answer & Explanation Answer: C) positive ion

Explanation:

If it loses an electron it becomes a positive ion

Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

1 2363
Q:

Which group in an ecosystem performs photosynthesis?

A) Xylotrophs B) Autotrophs
C) Monotrophs D) Heterotrophs
 
Answer & Explanation Answer: B) Autotrophs

Explanation:

In an ecosystem, Autotrophs performs photosynthesis. Autrophs are those prepare their own food.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

1 2362
Q:

Which of the following cities, is also known as the City of Festivals?

A) Madurai B) Varanasi
C) Puri D) Odisha
 
Answer & Explanation Answer: A) Madurai

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2362
Q:

The 'IC' chip, used in computers, is made of

A) Iron Oxide B) Silicon
C) Chomium D) Silica
 
Answer & Explanation Answer: B) Silicon

Explanation:
Report Error

View Answer Report Error Discuss

7 2362
Q:

The Longest Driverless Metro in the world is________

Answer

The Dhubai Metro(UAE) consists of two driverless lines(Red and Green) that totalled 74.694 km (46.41 miles) when the Greenline was officially opened on 9 September 2011.

Report Error

View answer Workspace Report Error Discuss

1 2362