Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ?

Answer

I. Inputs



  • Schedule management plan

  • Schedule baseline

  • Performance reports

  • Approved change requests


II. Tools and Techniques



  • Progress reporting

  • Schedule change control system

  • Performance measurement

  • Project management software

  • Variance analysis

  • Schedule comparision bar charts


III. Outputs



  • Schedule model data (updates)

  • Schedule baseline (updates)

  • Performance measurements

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Activity list (updates)

  • Activity attributes (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2101
Q:

The credit of inventing the television goes to

A) Philo Farnsworth B) John Logie Baird
C) Charles Francis Jenkins D) None of the above
 
Answer & Explanation Answer: A) Philo Farnsworth

Explanation:

The credit of inventing the television goes to Philo Farnsworth. Electronic television was first successfully demonstrated in San Francisco on Sept. 7, 1927.

 

The_credit_of_inventing_the_television_goes_to1549279715.jpg image

Report Error

View Answer Report Error Discuss

Filed Under: Inventions
Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

0 2100
Q:

Hub works on which layer?

A) Network layer B) Physical layer
C) Data link layer D) All of the above
 
Answer & Explanation Answer: B) Physical layer

Explanation:

Hub works on layer 1 i.e, physical layer.

Report Error

View Answer Report Error Discuss

Filed Under: Computer
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

3 2100
Q:

Hypercalcemia can be caused by

A) malignancy B) hyper-parathyroidism
C) both A & B D) None of the above
 
Answer & Explanation Answer: C) both A & B

Explanation:

Hypercalcemia is a condition in which the calcium level in your blood is above normal. Too much calcium in your blood can weaken your bones, create kidney stones, and interfere with how your heart and brain work.

Hypercalcemia_can_be_caused_by1550553960.png image

Hypercalcemia is usually a result of overactive parathyroid glands.

Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2100
Q:

At which stage in its life cycle does the silkworm yield the fiber of commercial use

A) Larva B) Egg
C) Pupa D) Imago
 
Answer & Explanation Answer: C) Pupa

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: Bank Exams

3 2100
Q:

What is the function of reverse transcriptase?

A) synthesis of RNA from protein B) synthesis of DNA from an RNA template
C) synthesis of protein from DNA D) synthesis of DNA from protein
 
Answer & Explanation Answer: B) synthesis of DNA from an RNA template

Explanation:

A reverse transcriptase (RT) is an enzyme used to generate complementary DNA (cDNA) from an RNA template by a process called Reverse Transcription.

In brief its function is that copies all or part of the virus RNA (retroviruses are RNA-only) as DNA which can then be integrated into the DNA of the host organism.

Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank PO

2 2099
Q:

Which membrane is highly convoluted?

A) the chloroplast outer membrane B) chloroplast inner membrane
C) both the mitochondrial and chloroplast outer membranes D) mitochondrial inner membrane
 
Answer & Explanation Answer: D) mitochondrial inner membrane

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

3 2099
Q:

Project Scope Management

What are the Project Management Processes included in the Project Scope Management?

Answer

Scope Planning - Creating a project scope management plan that documents how the project scope will be defined,verified, controlled, and how the work breakdown structure (WBS) will be created and defined.


Scope Definition - Developing a detailed project scope statement as the basis for future project decisions.


Create WBS - Subdividing the major project deliverables and project work into smaller, more manageable components


Scope Verification - Formalizing acceptance of the completed project deliverables.


Scope Control - Controlling changes to the project scope.

Report Error

View answer Workspace Report Error Discuss

0 2098