Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets 

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary 

  • Project management plan


             - Schedule management plan


             - Staffing management plan


             - Risk register


II. Tools and Techniques



  • Analogous estimating

  • Determine resource cost rates

  • Bottom-up estimating

  • Parametric estimating

  • Project management software

  • Vendor bid analysis

  • Reserve analysis

  • Cost of quality


III. Outputs



  • Activity cost estimates 

  • Activity cost estimate supporting detail 

  • Requested changes

  • Cost management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2089
Q:

The 45th World Skills Competition 2019 will take place in which of the following country?

A) India B) Russia
C) Finland D) South Korea
 
Answer & Explanation Answer: B) Russia

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Sports
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

3 2089
Q:

In the following question, out of the four alternatives, choose the word which best expresses the meaning of the given word and click the buttoncorresponding to it.

CONSTRAIN

A) STRESS B) CONTRADICT
C) RESTRICT D) OBSTRUCT
 
Answer & Explanation Answer: C) RESTRICT

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2089
Q:

In the following question, out of the four alternatives, select the alternative which best expresses the meaning of the idiom/phrase.
Kick the bucket

A) Loose temper B) To delay a little longer
C) To die D) To meet with an accident
 
Answer & Explanation Answer: C) To die

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2089
Q:

In the following question, out of the given four alternatives, select the one which is opposite in meaning of the given word.

Forgo

A) Forfeit B) Neglect
C) Conquer D) Pass
 
Answer & Explanation Answer: C) Conquer

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2088
Q:

The size of the pupil is controlled by the

A) Retina B) Iris
C) Cornea D) Lens
 
Answer & Explanation Answer: B) Iris

Explanation:

The size of the pupil is controlled by the Iris when light enters the eye.

Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

3 2088
Q:

Magnesium (Mg) + Oxygen (O2) = ?

A) Mg2O B) MgO4
C) O2Mg D) MgO
 
Answer & Explanation Answer: D) MgO

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Chemistry
Exam Prep: Bank Exams

4 2088
Q:

Project Time Management

What are the Project Management Processes included in the Project Time Management?

Answer

Activity Definition - Identifying the Specific schedule activities that need to be performed to produce the various project deliverables.


Activity Sequencing - Identifying and documenting dependencies among schedule activities


Activity Resource Estimating - Estimating the type and quantities of resources required to perform each schedule activity


Activity Duration Estimating - Estimating the number of work periods that will be needed to complete individual schedule activities


Schedule Development - Analyzing activity sequences, durations, resource requirements, and schedule constraints to creae the project schedule.


Schedule Control - Controlling changes to the project schedule

Report Error

View answer Workspace Report Error Discuss