Questions

Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 5284
Q:

Curie is the unit of

A) temparature B) radio activity
C) heat D) energy
 
Answer & Explanation Answer: B) radio activity

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics

7 5283
Q:

______ is the first state to have Logo for Vehicles Driven by person with Hearing Impairment ?

A) Telangana B) Rajasthan
C) Gujarat D) Haryana
 
Answer & Explanation Answer: A) Telangana

Explanation:

Telangana has introduced a logo for identifying vehicles driven by persons with hearing impairment and has become the first state in the country to do so. 

The logo was designed by city-based graphic designer Manikanta Annapragada who was the first person to obtain a driving licence under the ‘hearing impaired’ category in the country.

The logo consists of a hearing impaired mark along with text saying, “Driver is deaf — Please watch out”.

Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Bank Clerk

5 5278
Q:

The book " Truth, love and A Little Malice " is written by 

A) Tarun Tejpal B) Vikram Seth
C) Khushwant Singh D) Nirad C. Chaudhuri
 
Answer & Explanation Answer: C) Khushwant Singh

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Books and Authors

8 5278
Q:

Which is the folk dance of Andhra Pradesh?

A) Kolattam B) Karakattam
C) Lavani D) Saturi
 
Answer & Explanation Answer: A) Kolattam

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Culture

62 5278
Q:

Parasec is ythe unit of

A) distance B) time
C) intensity of light D) magnetic line
 
Answer & Explanation Answer: A) distance

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics

3 5277
Q:

The construction of world’s largest optical telescope has started in which country  ?

A) China B) Russia
C) Chile D) India
 
Answer & Explanation Answer: C) Chile

Explanation:

The construction of the world’s largest optical telescope has started in northern Chile, which is expected to begin operating in 2024. The Extremely Large Telescope (ELT) is being built by the European Southern Observatory (ESO) and will have a main mirror that is 39m in diameter. The telescope will be positioned on top of Cerro Armazones – a 3046-metre long mountain Chile. It will tackle a wide range of scientific challenges, including probing Earth-like exoplanets for signs of life, studying the nature of dark energy and dark matter, and observing the universe’s early stages to explore humans’ origins.

Report Error

View Answer Report Error Discuss

Filed Under: Longest, Shortest, Deepest
Exam Prep: Bank Exams
Job Role: Bank Clerk

14 5276
Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 5276