Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Qualitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement 

  • Risk management plan

  • Risk register


II.  Tools and Techniques



  • Risk probability and impact assesment

  • Probability and impact matrix

  • Risk data quality assessment

  • Risk categorization 

  • Risk Urgency assessment


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 2133
Q:

Who among the following, played an important role in the struggle for italian independence and unification?

A) Bismarck B) Giuseppe Mazzini
C) Giuseppe Garibaldi D) Both (b) and (c)
 
Answer & Explanation Answer: D) Both (b) and (c)

Explanation:

The struggle for Italian independence and unification was organised by the two famous revolutionaries of Italy Giuseppe Mazzini and Giuseppe Garibaldi. The movement led by them is known as the 'Young Italy' movement. It aimed at the independence and unification of Italy and the establishment of republic there.

Report Error

View Answer Report Error Discuss

Filed Under: World History

0 2133
Q:

What's the speed and device maximum specs for Firewire?

Answer

IEEE 1394 (Firewire) supports the maximum of 63 connected devices with speeds upto 400 Mbps.

Report Error

View answer Workspace Report Error Discuss

Subject: Hardware

0 2133
Q:

Mutual Funds are regulated in India by

A) SEBI B) RBI
C) RBI & SEBI both D) Stock Exchanges
 
Answer & Explanation Answer: A) SEBI

Explanation:

Mutual Funds are regulated in India by SEBI (Securities and Exchange Board of India). It was founded in 1992. In 1996, SEBI formulated the Mutual Fund Regulation.

Report Error

View Answer Report Error Discuss

Filed Under: Indian Economy
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

1 2133
Q:

In the following question, a sentence has been given in Direct/Indirect speech. Out of the four alternatives suggested, select the one which best
expresses the same sentence in Indirect/Direct speech.
Rohit said, "I take a bath daily with cold water."

A) Rohit says that he were taking a bath daily with cold water. B) Rohit said that he has had been taking a bath daily with cold water.
C) Rohit said that he is taking a bath daily with cold water. D) Rohit said that he took a bath daily with cold water.
 
Answer & Explanation Answer: D) Rohit said that he took a bath daily with cold water.

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English

0 2132
Q:

Isfahan, the Persian Capital is said to have provided the inspiration to build which of these monuments?

A) Humayun's Tomb B) Mahabodhi Temple Complex
C) Qutub Minar D) Red Fort Complex
 
Answer & Explanation Answer: D) Red Fort Complex

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Geography
Exam Prep: Bank Exams

1 2132
Q:

In Geography, who propounded the theory of convectional current Hypothesis?

A) Carl Ritter B) Immanuel Kant
C) Arthur Holmes D) Arnaldo Faustini
 
Answer & Explanation Answer: C) Arthur Holmes

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Geography
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2132
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Development?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Project schedule network diagrams

  • Activity resource requirements

  • Resource calendars

  • Activity duration estimates 

  • Project management plan


                - RisK register


II. Tools and Techniques



  • Schedule network analysis

  • Critical path method

  • Schedule compression

  • What-if scenario analysis

  • Resource leveling

  • Critical chain method

  • Project management software

  • Applying calendars

  • Adjusting leads and lags 

  • Schedule model


III. Outputs



  • Project schedule

  • Schedule model data

  • Schedule baseline

  • Resource requirements (updates)

  • Activity attributes (updates)

  • Project calendar (updates)

  • Requested changes

  • Project management plan (updates)


                 - Schedule management plan(updates)

Report Error

View answer Workspace Report Error Discuss

0 2132