Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project scope management plan

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Change control system

  • Variance analysis

  • Replanning

  • Configuration management system


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure(updates)

  • WBS dictionary (updates)

  • Scope baseline (updates)

  • Requested changes

  • Recommended  corrective action

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2154
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ?

Answer

I. Inputs



  • Schedule management plan

  • Schedule baseline

  • Performance reports

  • Approved change requests


II. Tools and Techniques



  • Progress reporting

  • Schedule change control system

  • Performance measurement

  • Project management software

  • Variance analysis

  • Schedule comparision bar charts


III. Outputs



  • Schedule model data (updates)

  • Schedule baseline (updates)

  • Performance measurements

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Activity list (updates)

  • Activity attributes (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2154
Q:

Project Life Cycle

What is the Project Life Cycle?

Answer

Project managers or the organization can divide projects into phases to provide better management control with appropriate links to the ongoing operations of the performing organization. Collectively, these phases are known as the project life cycle.

Report Error

View answer Workspace Report Error Discuss

0 2154
Q:

Where does transcription occur in the cell?

A) Cytoplasm B) Nucleus
C) Ribosome D) None of the above
 
Answer & Explanation Answer: B) Nucleus

Explanation:

Transcription is a process of production of mRNA which occurs in the nucleus of the cell. After transcription, translation which occurs in the cytoplasm.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2154
Q:

Rate at which velocity changes over time?

A) Speed B) Displacement
C) Acceleration D) Jerk
 
Answer & Explanation Answer: C) Acceleration

Explanation:

Acceleration is nothing but the rate at which velocity changes over time.

Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

7 2154
Q:

Where is the RAM located in a computer?

A) Monitor B) Processor
C) Mother board D) None of the above
 
Answer & Explanation Answer: C) Mother board

Explanation:

On the right corner of the mother board RAM is located in a computer.

Report Error

View Answer Report Error Discuss

3 2154
Q:

Enumerators are stored by the compiler in

A) integer B) string
C) float D) any of above
 
Answer & Explanation Answer: A) integer

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Computer
Exam Prep: Bank Exams

3 2154