Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Control ?

Answer

I. Inputs



  • Cost baseline

  • Project funding requirements

  • performance reports

  • Work performance information

  • Approved change requests

  • Project management plan


II. Tools and Techniques



  • Cost change control system

  • Performance measurement analysis

  • Forecasting

  • Project performance reviews

  • Project management software 

  • Variance management


III. Outputs



  • Cost estimate (updates)

  • Cost baseline (updates)

  • Performance measurements

  • Forecasted completion

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)


 

Report Error

View answer Workspace Report Error Discuss

0 2674
Q:

How many Indians have so far been awarded the Nobel Prize

A) 2 B) 3
C) 4 D) More than 4
 
Answer & Explanation Answer: D) More than 4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Honours and Awards

0 2674
Q:

Project Management - Introduction

What is Project Management?

Answer

Project Management is the application of Knowledge, skills, tools and techniques to project activities to meet project requirements. Project Management is accomplished through the application and integraton of the project management processes of  initiating, planning, executing, monitoring and controlling , closing.

Report Error

View answer Workspace Report Error Discuss

0 2673
Q:

Which of these was a political goal for farmers?

A) lower prices for grain storage B) higher prices for machinery
C) lower prices for foreign goods D) higher prices for shipping
 
Answer & Explanation Answer: A) lower prices for grain storage

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO , Database Administration

6 2673
Q:

Mount Everest is located between

 

A) China & India B) India & Nepal
C) China & Nepal D) India & Myanmar
 
Answer & Explanation Answer: C) China & Nepal

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Geography
Exam Prep: Bank Exams

5 2673
Q:

The only known ruler in the history of india to have fixed the prices of different commodities, rigidly enforced quality control and ensured easy availability of essential commodities was

A) lltutmish B) Alauddin Khalji
C) Raziya D) Gayasuddin Tughluq
 
Answer & Explanation Answer: B) Alauddin Khalji

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History

2 2672
Q:

What is thrashing?

Answer

It is a phenomenon in virtual memory schemes when the processor spends most of its time swapping pages, rather than executing instructions. This is due to an inordinate number of page faults.

Report Error

View answer Workspace Report Error Discuss

0 2672
Q:

Which team advanced to the Coap America Finals 2011 without winning any of its five matches in open play?

A) Brazil B) Paraguay
C) Venezuela D) Peru
 
Answer & Explanation Answer: B) Paraguay

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Sports

2 2672