Questions

Q:

What is a word made up of 4 letters, yet is also made up of 3. Everything is written with 9 letters, and then with 4. Rarely consists of 6, and never is written with 5.

Answer

The Riddle itself has the Answers.


What is a 4 letter word


Yet is written in 3 letters


Everything is written with 9 letters


Then with 4 letters


Rarely has 6 letters


Never is written in 5 letters.

Report Error

View answer Workspace Report Error Discuss

9 2271
Q:

I have an eye but cannot see?

Answer

Its a Needle. Needle has an eye but can't see.

Report Error

View answer Workspace Report Error Discuss

6 2271
Q:

The bar graph shows the number of employees working in the different departments of a company. Study the diagram and answer the following questions

Which department has the lowest number of employees?

A) C B) D
C) A D) B
 
Answer & Explanation Answer: B) D

Explanation:
Report Error

View Answer Report Error Discuss

1 2271
Q:

What is time-stamping?

Answer

It is a technique proposed by Lamport, used to order events in a distributed system without the use of clocks. This scheme is intended to order events consisting of the transmission of messages. Each system 'i' in the network maintains a counter Ci. Every time a system transmits a message, it increments its counter by 1 and attaches the time-stamp Ti to the message. When a message is received, the receiving system 'j' sets its counter Cj to 1 more than the maximum of its current value and the incoming time-stamp Ti. At each site, the ordering of messages is determined by the following rules: For messages x from site i and y from site j, x precedes y if one of the following conditions holds....(a) if Ti

Report Error

View answer Workspace Report Error Discuss

1 2270
Q:

What are the original member states in Bank of Central African states

A) 5 B) 4
C) 3 D) 2
 
Answer & Explanation Answer: A) 5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Organisations

0 2270
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Response Planning?

Answer

I. Inputs



  • Risk management plan

  • Risk register


II. Tools and Techniques



  • Strategies for negative risk or threats

  • Strategies for positive risks or opportunities

  • Strategies for both threats and opportunities

  • Contingent response strategy


III. Outputs



  • Risk register (updates)

  • Project management plan (updates)

  • Risk - related contractual agreements

Report Error

View answer Workspace Report Error Discuss

0 2270
Q:

Which section of IT Act of 2000 has been scraped to avoid people being prosecuted?

A) 66A B) 96A
C) 69A D) 76A
 
Answer & Explanation Answer: A) 66A

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Politics
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2270
Q:

Project Stakeholders

What do you meant by project stakeholders?

Answer

Project Stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.


Stakeholders may have a positive or negative.


Positive stakeholders are those who would normally benefit from a successful outcome from the project, while negative stakeholders are those who see negative outcomes from the project's success.

Report Error

View answer Workspace Report Error Discuss

0 2269