Questions

Q:

In the following question, out of the given four alternatives, select the one which best expresses the meaning of the given word

Arbitrary

A) Methodical B) Penetrable
C) Random D) Artful
 
Answer & Explanation Answer: C) Random

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: CAT , GRE , TOEFL
Job Role: Bank Clerk , Bank PO

0 2128
Q:

Who holds the record for most times for Oscar Noms?

A) Walt Disney B) James Cameron
C) Steven Spielberg D) Ridley Scott
 
Answer & Explanation Answer: A) Walt Disney

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Famous Personalities
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2128
Q:

India’s who has won the girl's title in the IBSF World Under-16 Snooker Championships 2018?

A) Keerthana Pandian B) Sangeeta Chanu
C) Kumar Mangalan D) Thangjam Tababi Devi
 
Answer & Explanation Answer: A) Keerthana Pandian

Explanation:

India's Keerthana Pandian has won the girls’ title in the IBSF World Under-16 Snooker Championships.

 

In the final in St Petersburg, Russia, Keerthana outclassed her Belarussian rival Albina Leschuk 3-1.

Report Error

View Answer Report Error Discuss

Filed Under: Sports
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2128
Q:

Select the antonym of
mishmash

A) potpourri B) medley
C) organized D) haphazard
 
Answer & Explanation Answer: C) organized

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2128
Q:

A doctor who specializes in skin diseases

A) Nephrology B) Dermatology
C) Paediatrician D) Rheumatology
 
Answer & Explanation Answer: B) Dermatology

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

6 2128
Q:

What is the general formula for a straight-chain alkane?

A) C2nH2n+3. B) CnH2n+2
C) CnH2n D) CnH3n+2.
 
Answer & Explanation Answer: B) CnH2n+2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Chemistry
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

1 2127
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Development?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Project schedule network diagrams

  • Activity resource requirements

  • Resource calendars

  • Activity duration estimates 

  • Project management plan


                - RisK register


II. Tools and Techniques



  • Schedule network analysis

  • Critical path method

  • Schedule compression

  • What-if scenario analysis

  • Resource leveling

  • Critical chain method

  • Project management software

  • Applying calendars

  • Adjusting leads and lags 

  • Schedule model


III. Outputs



  • Project schedule

  • Schedule model data

  • Schedule baseline

  • Resource requirements (updates)

  • Activity attributes (updates)

  • Project calendar (updates)

  • Requested changes

  • Project management plan (updates)


                 - Schedule management plan(updates)

Report Error

View answer Workspace Report Error Discuss

0 2127
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project scope management plan

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Change control system

  • Variance analysis

  • Replanning

  • Configuration management system


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure(updates)

  • WBS dictionary (updates)

  • Scope baseline (updates)

  • Requested changes

  • Recommended  corrective action

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error