Q:
Project Time Management - Processes
Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ?
Answer
I. Inputs
- Schedule management plan
- Schedule baseline
- Performance reports
- Approved change requests
II. Tools and Techniques
- Progress reporting
- Schedule change control system
- Performance measurement
- Project management software
- Variance analysis
- Schedule comparision bar charts
III. Outputs
- Schedule model data (updates)
- Schedule baseline (updates)
- Performance measurements
- Requested changes
- Recommended corrective actions
- Organizational process assets (updates)
- Activity list (updates)
- Activity attributes (updates)
- Project management plan (updates)
View answer