Q:

Type 1 workers are 2.5 times as efficient as type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 15 Type 2 workers to do the same work?

 

A) 13 B) 10
C) 12 D) 11
 
Answer & Explanation Answer: D) 11

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

Q:

10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the task?

A) 7 B) 8
C) 6 D) 5
 
Answer & Explanation Answer: C) 6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

Q:

Multitasking system specifically refers to

A) More than one user B) More than one process
C) More than one hardware D) More than one IP address
 
Answer & Explanation Answer: B) More than one process

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Computer
Exam Prep: Bank Exams

Q:

A and B can complete a task in 20 days, B and C can complete it in 30 days while C and A can do the same task together in 24 days. How many days will each of and C take to complete the task individually? 

 

A) 50 and 54  B) 54 and 72 
C) 48 and 80  D) 56 and 64
 
Answer & Explanation Answer: C) 48 and 80 

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

Q:

30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task?

A) 12 days B) 10 days
C) 15 days D) 18 days
 
Answer & Explanation Answer: B) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

Q:

A, B and C can complete a task together in 10 days. A and B would need 12 days if only the two of them worked, while B and C would take 20 days if only the two of them worked. If B worked alone, how many days would she take to complete the task?

A) 30 B) 22
C) 45 D) 20
 
Answer & Explanation Answer: A) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

Q:

A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and competes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?

A) 18 B) 22
C) 20 D) 15
 
Answer & Explanation Answer: C) 20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams