Q:

Which screen area(s) in the transaction for goods movements MIGO cannot be closed?

A. Item overview

B. Header data

C. Overview tree

D. Detail data for item

Answer

Answer : A


 


Explanation: Excluding the item overview, you can open and close all screen  areas
individual ly in the MIGO transaction.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

3 4423
Q:

Which of the following statements about VPRS(cost) are correct?

A. It is controled by the customer master

B. A condition type VPRS is a statistical condition type

C. A condition record can be created for a condition type VPRS (cost)

D. It is controled by the material master

Answer

Answer : B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP SD

2 4379
Q:

We must settle all line items at once, and you do not have to distribute100 percent of each line item for AUC using line item settlement.

A) TRUE B) FALSE
Answer & Explanation Answer: B) FALSE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

Subject: SAP FI

0 4363
Q:

The three tier in R/3 system is represented by

A. user, data base, programs

B. application, data base and customer of R/3

C. presentation client, R/3 application and data base

D. data, user and application

Answer

Answer : C

Report Error

View answer Workspace Report Error Discuss

Subject: SAP FI

4 4351
Q:

How can you store long-term prices for services in the form of service conditions?

A. At the service and plant level

B. At the service and vendor level

C. At the service level

D. At the service, vendor and plant level

Answer

Answer: B , C , D


 


Explanation: Long term prices can be maintained at Service level, Service and Vendor level or Service, Vendor and Plant level.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

11 4156
Q:

Types of depreciation in Asset accounting.Choose the following?

A.Special depreciation            B.Unplanned depreciation

C.Manual depreciation           D.Automatic depreciation

Answer

Answer : A , B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP FI

0 4134
Q:

We can use schedule manager in FI-AA to define, schedule,process and control periodically recurring processes.

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

Subject: SAP FI

0 4131
Q:

Which of the following master data can/must you use for pipeline meterials?

A. BOM(ascomponent)

B. Purchasing info record

C. Material master record

D. Vendor master record

E. Source list

Answer

Answer : A , B , C , D , E [all these]


 


Explanation:You must have created a material master record with a purchasing info record. To do this, you need a vendor master record. You can use the source list and BOM in connection with the pipeline material.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

8 4089