Searching for "at"

Q:

The fish that can taste with its whole body is the

Answer

Catfish

Report Error

View answer Workspace Report Error Discuss

Q:

The only fish that makes nest is the

Answer

Stickle back

Report Error

View answer Workspace Report Error Discuss

Q:

What is the largest seabird ?

Answer

Albatross

Report Error

View answer Workspace Report Error Discuss

Q:

In which of the following animals is respiration done by skin?

A) Flying fish B) Sea horse
C) Frog D) Chemeleon
 
Answer & Explanation Answer: C) Frog

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Animals and Birds

Q:

In which of the following kinds of organism is the phenomenon found wherein the female kills the male after copulation

A) Dragonfly B) Honeybee
C) Spider D) Pit viper
 
Answer & Explanation Answer: B) Honeybee

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Animals and Birds

Q:

Among the following animals , the figures of which are found in the state emblem of india?

A) Bull, deer and eagle B) Deer and elephant
C) Elephant, Tiger and Bull D) Horse and Bull
 
Answer & Explanation Answer: D) Horse and Bull

Explanation:

Refer National symbols

Report Error

View Answer Report Error Discuss

Filed Under: Animals and Birds

Q:

If 20 men can build a wall 56 meters long in 6 days , what length of  a similar wall can be  built by 35 men in 3 days?

A) 46 B) 47
C) 48 D) 49
 
Answer & Explanation Answer: D) 49

Explanation:

Let the required length be x meters

 More men, More length built     (Direct proportion) 

Less days, Less length built      (Direct Proportion)

Men20:35Days6 : 3 56 :x 

=> (20 x 6 x X)=(35 x 3 x 56) 

=> x = 49 

Hence, the required length is 49 m.

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

Q:

A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the begining and 100 more  after 35 days and completes the work in stipulated time. If he had not  engaged  the additional men, how many days  behind schedule would it be finished?

A) 3 B) 5
C) 6 D) 9
 
Answer & Explanation Answer: B) 5

Explanation:

[(100 x 35) + (200 x 5)]men can finish the work in 1 day 

Therefore, 4500 men can finish the work in 1 day. 100 men can finish it in  4500/100= 45 days.

This is 5 days behind Schedule

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule