Q:

Which of the following master data can/must you use for pipeline meterials?

A. BOM(ascomponent)

B. Purchasing info record

C. Material master record

D. Vendor master record

E. Source list

Answer

Answer : A , B , C , D , E [all these]


 


Explanation:You must have created a material master record with a purchasing info record. To do this, you need a vendor master record. You can use the source list and BOM in connection with the pipeline material.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

Q:

Which of the following MRP areas do not exist?

A. Consignment MRP area
B. Plant MRP area
C. Storage location MRP area
D. Subcontractor MRP area

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

Q:

The following are lot sizing rules available for SAP R/3?

A. Replenish to maximum stock level
B. Weekly lot size
C. Daily lot size
D. Fixed lot size

Answer

Answer : A ,B ,C

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

Q:

Which transaction shows the most up to date planning data?

A. Stock Requirement list

B. MRP list

C. Stock Overview report

D. List display of material and accounting documents

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

Q:

What is the purpose of specifying a planning horizon?

A.  Only materials manifesting a planning-relevant change within the planning horizon are taken into account in the MRP run (where NETPL is used).
B.  To specify whether forecasts are included in the material requirement calculation.

C. To specify that only externally procured (and not internally procured) items are included in the net change MRP run.

D. To specify whether a NETCH (net change in complete horizon) or a NETPL (net change in planning horizon) will take place in the next MRP run.

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

Q:

You enter a goods issue and receive the following message: "W: On , only 0.000 pieces are available". What do you conclude from this?

A. The message represents a warning which you can ignore by pressing the ENTER key.

B. The material exist in the specified storage location on the current day, however, it is unavailable, because of other reservations.

C. No stocks of the material exist anywhere in the entire plant.  Therefore, nothing can be withdrawn

D. Only the specified storage location does not contain any stocks of the material.  Therefore, nothing can be withdrawn.

Answer

Answer : A , B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

Q:

How can you store long-term prices for services in the form of service conditions?

A. At the service and plant level

B. At the service and vendor level

C. At the service level

D. At the service, vendor and plant level

Answer

Answer: B , C , D


 


Explanation: Long term prices can be maintained at Service level, Service and Vendor level or Service, Vendor and Plant level.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

Q:

Which of the following statements apply to the parameter EFB?The parameter EFB enables you to determine whether

A. The planned delivery time is checked against the delivery date during the source determination process.

B. The conditions in an outline purchase agreement are displayed to a user.

C. A user may create a PO without reference to a preceding document

D. The price from the last purchase order appears as the default value when a new PO is created.

Answer

Answer : B , C


 


Explanation: Statements A and D apply not to parameter EFB, but to parameter EVO

Report Error

View answer Workspace Report Error Discuss