0
Q:

A and B can do a piece of work in 40 and 50 days. If they work at it an alternate days with A beginning in how many days, the work will be finished ? 

Answer:
Q:

A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time ?

A) 2 days B) 3 days
C) 4 days D) 5 days
 
Answer & Explanation Answer: A) 2 days

Explanation:

work done=total number of person x number of days;
half of work done = 140 x 66;
For half of remaining work 25 extra men are added.
Therefore, total men for half work remaining = 140 + 25 = 165;
Let 2nd half work will be completed in K days;
140 x 66 = 165 x K
K = 122;
Hence, extra days => 122-120 = 2days.

Report Error

View Answer Workspace Report Error Discuss

1 29
Q:

A,B,C together can do a piece of work in 10 days.All the three started workingat it together and after 4 days,A left.Then,B and C together completed the work in 10 more days.In how many days can complete a work alone ?

A) 25 B) 24
C) 23 D) 21
 
Answer & Explanation Answer: A) 25

Explanation:

(A+B+C) do 1 work in 10 days.
So (A+B+C)'s 1 day work=1/10 and as they work together for 4 days so workdone by them in 4 days=4/10=2/5
Remaining work=1-2/5=3/5
(B+C) take 10 more days to complete 3/5 work.
So( B+C)'s 1 day work=3/50
Now A'S 1 day work=(A+B+C)'s 1 day work-(B+C)'s 1 day work=1/10-3/50=1/25
A does 1/25 work in in 1 day
Therefore 1 work in 25 days.

Report Error

View Answer Workspace Report Error Discuss

1 25
Q:

A can write 32 pages in 6 hours and B can write 40 pages in 5 hours. If they write together, in how many hours they can write 110 pages ?

A) 7 hrs B) 6 hrs 10 min
C) 5 hrs 25min D) 8 hrs 15 min
 
Answer & Explanation Answer: D) 8 hrs 15 min

Explanation:

A can write in 1hour = 32/6 pages
similarly
B in 1 hour = 40/5 pages

Together (A+B) in 1 hour = 32/6 + 40/5 = 40/3
so,
A+B write 40/3 pages in 1 hour
A+B write 110 pages in (3/40) x 110 Hours = 8 hours 15 min.

Report Error

View Answer Workspace Report Error Discuss

1 40
Q:

There is sufficient salary to give K for 10 days and L for 15 days. Then how many days will the money last if both has to be given the salary ?

A) 6 days B) 12 days
C) 4 days D) 9 days
 
Answer & Explanation Answer: A) 6 days

Explanation:

K's 1 day's salary = 1/10
L's 1 day's salary = 1/15
Together their 1 day's salary = 1/10 + 1/15
= 3/30 + 2/30
= 5/30
= 1/6
So the money will be
enough for paying them both for 6 days.

Report Error

View Answer Workspace Report Error Discuss

1 30
Q:

4 men can repair a road in 7 hours. How many men are required to repair the road in 2 hours ?

A) 17 men B) 14 men
C) 13 men D) 16 men
 
Answer & Explanation Answer: B) 14 men

Explanation:

M x T / W = Constant
where, M= Men (no. of men)
T= Time taken
W= Work load
So, here we apply
M1 x T1/ W1 = M2 x T2 / W2
Given that, M1 = 4 men, T1 = 7 hours ; T2 = 2 hours, we have to find M2 =?
Note that here, W1 = W2 = 1 road, ie. equal work load.
Clearly, substituting in the above equation we get, M2 = 14 men.

Report Error

View Answer Workspace Report Error Discuss

2 52