3
Q:

A and B together can do a piece of work in 40 days. A having worked for 20 days, B finishes the remaining work alone in 60 days. In How many days shall B finish the  whole work alone?

A) 60 B) 70
C) 80 D) 90

Answer:   C) 80

Explanation:

Let A's 1 day's work=x and B's 1 day's work=y

Then x+y =\inline {\color{Black} \frac{1}{40}} and 20x+60y=1

Solving these two equations , we get : x=\inline {\color{Black} \frac{1}{80}} and y=\inline {\color{Black} \frac{1}{80}}

\inline {\color{Black} \therefore } B's  1 day work = \inline {\color{Black} \frac{1}{80} }

Hence,B alone shall finish the whole work in 80 days

Q:

Sixty men can stitch 150 shirts in 30 days working 8 hours a day. In how many days can 35 men stitch 200 shirts working 6 hours a day ?

A) 87.5 B) 89
C) 91.5 D) 93.5
 
Answer & Explanation Answer: C) 91.5

Explanation:

We have M1 D1 H1 / W1 = M2 D2 H2 / W2 (Variation rule)
(60 x 30 x 8)/ 150 = (35 x D2 x 6) / 200
D2 = (60 x 30 x 8 x 200) / (150 x 35 x 6) => D2 = 91.42 days =~ 91.5 days.

Report Error

View Answer Workspace Report Error Discuss

1 17
Q:

A can complete a piece of work in 12 days and B is 60% more efficient than A. In how many days B will complete the same work  ?

A) 8.7 hrs B) 5.2 hrs
C) 5 hrs D) 7.5 hrs
 
Answer & Explanation Answer: D) 7.5 hrs

Explanation:

Ratio of times taken by A and B = 160 : 100
A can do the work in 12 days
Let B can do the work in "D" days
=> 160:100 = 12 : D
=> D = 12 x 100/160 = 7.5 hrs

Report Error

View Answer Workspace Report Error Discuss

2 50
Q:

A can finish a work in 18 days and B can do the same work in half the time taken by A. then, working together, what part of the same work they can finish in a day ?

A) Total work B) One-fourth work
C) Half work D) Two-third work
 
Answer & Explanation Answer: C) Half work

Explanation:

A can do the work = 18 days
B can do the work = 18/2 = 9 days
(A + B)'s 1 day work = 1/18 + 1/9 = 1/6
=> In 3 days = 3x1/6 = 1/2 work is completed.

Report Error

View Answer Workspace Report Error Discuss

1 35
Q:

10 boys can complete a work in 7 days and 10 girls take 14 days to complete the work. How many days will 5 boys and 10 girls take to complete the work ?

A) 13 days B) 10 days
C) 7 days D) 16 days
 
Answer & Explanation Answer: C) 7 days

Explanation:

1 boy's 1 day work = 1/70
1 girl's 1 day work = 1/140
(5 boys + 10 girls)'s 1 day work
= (5/70 + 10/140) = (1/14 + 1/14) = 1/7

5 boys and 10 girls will complete the work in 7 days.

Report Error

View Answer Workspace Report Error Discuss

2 50
Q:

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days  ?

A) 9 days B) 11 days
C) 13 days D) 15 days
 
Answer & Explanation Answer: C) 13 days

Explanation:

Ratio of times taken by A and B = 100 : 130 = 10 : 13.
Suppose B takes x days to do the work.

Then, 10 : 13 :: 23 : x     =>     x = ( 23 x 13/10 )     =>     x = 299 /10.

A's 1 day's work = 1/23 ;
B's 1 day's work = 10/299 .

(A + B)'s 1 day's work = ( 1/23 + 10/299 ) = 23/299 = 113 .

Therefore, A and B together can complete the work in 13 days. 

Report Error

View Answer Workspace Report Error Discuss

1 60