3
Q:

A contractor  undertook a project to complete it in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that  he needed to increase 5 additional  men every 2 days to complete the work in the time the client wanted it:

If the work was further increased by 50% but the contractor continues to increase the 5 workers o every 2 days then how many more days are required over the initial time specified by the  client.

A) 1 day B) 2 days
C) 5 days D) None of these

Answer:   B) 2 days

Explanation:

Total work = 100+50 = 150man-days

In 8 days 100 man-days work  has been completed. Now on 9th and 10th day there will be 25 workers. So in 2 days they wll complete additional 50 man- days work. Thus the work requires 2 more days.

Q:

A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?

A) [7 + (215/345)] days B) [6 + (11/215)] days
C) [6 + (261/315)] days D) [5 + (112/351)] days
 
Answer & Explanation Answer: C) [6 + (261/315)] days

Explanation:

After day 1, A finishes 1/9 of the work.

After day 2, B finishes 1/7 more of the total work. (1/9) + (1/7) is finished.

After day 3, C finishes 1/5 more of total work. Total finished is 143/315.

So, after day 6, total work finished is 286/315.

Now remaining work = 315 - 286 = 29 /315

On day 7, A will work again

Work will be completed on day 7 when A is working. He must finish 29/315 of total remaining work.

Since he takes 9 days to finish the total task, he will need 261/315 of the day.

Total days required is 6 + (261/315) days.

Report Error

View Answer Workspace Report Error Discuss

1 11
Q:

One girl can eat 112 chocolates in half a minute, and her boy friend can eat half as many in twice the length of time. How many chocolates can both boy and girl eat in 12 seconds ?

A) 44 B) 32
C) 56 D) 49
 
Answer & Explanation Answer: C) 56

Explanation:

Girl eats 112 chocolates in 30 sec
so she can eat in 12 sec is 12 x 112/30 = 44.8 chocolates.

Her boy friend can eat one-half of 112 in twice of 30 sec
so he can eat 56 in 60 sec
Then he can eat in 12 sec is 56 x 12/60 = 11.2 chocolates.

Hence, together they can eat
=> 44.8 + 11.2
56 chocolates in 12 seconds.

Report Error

View Answer Workspace Report Error Discuss

5 10
Q:

Two boys and a girl can do a work in 5 days, while a boy and 2 girls can do it in 6 days. If the boy is paid at the rate of 28$ a week, what should be the wages of the girl a week ?

A) 24 $ B) 22 $
C) 16 $ D) 14 $
 
Answer & Explanation Answer: C) 16 $

Explanation:

Let the 1 day work of a boy=b and a girl=g, then
2b + g = 1/5 ---(i) and
b + 2g = 1/6 ---(ii)
On solving (i) & (ii), b=7/90, g=2/45
As payment of work will be in proportion to capacity of work and a boy is paid $ 28/week,
so a girl will be paid 28x  = 16 $.

Report Error

View Answer Workspace Report Error Discuss

3 9
Q:

A constructor estimates that 4 people can paint Mr. Karthik's house in 6 days. If he uses 5 people instead of 4, how long will they take to complete the job ?

A) 3 days B) 26/3 days
C) 13/4 days D) 24/5 days
 
Answer & Explanation Answer: D) 24/5 days

Explanation:

we know that m1 x d1 = m2 x d2
=> 4 x 6 = 5 x d
where d = no. of days taken by 5 men to paint
d = 24/5 days.

Report Error

View Answer Workspace Report Error Discuss

4 15
Q:

6 boys and 8 girls can do job in 10 days , 26 boys & 48 women do work in 2 days. Find time taken by 15 boys and 20 girls to do same work ?

A) 2 days B) 3 days
C) 4 days D) 5 days
 
Answer & Explanation Answer: C) 4 days

Explanation:

One day work of 6 boys and 8 girls is given as 6b + 8g = 1/10 -------->(I)
One day work of 26 boys and 48 women is given as 26b + 48w = 1/2 -------->(II)

Divide both sides by 2 in (I) and then multiply both sides by 5
Now we get
15b + 20g = 1/4.
Therefore, 15 boys and 20 girls can do the same work in 4 days.

Report Error

View Answer Workspace Report Error Discuss

5 13