4
Q:

A contractor  undertook a project to complete it in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that  he needed to increase 5 additional  men every 2 days to complete the work in the time the client wanted it:

If the work was further increased by 50% but the contractor continues to increase the 5 workers o every 2 days then how many more days are required over the initial time specified by the  client.

A) 1 day B) 2 days
C) 5 days D) None of these

Answer:   B) 2 days



Explanation:

Total work = 100+50 = 150man-days

In 8 days 100 man-days work  has been completed. Now on 9th and 10th day there will be 25 workers. So in 2 days they wll complete additional 50 man- days work. Thus the work requires 2 more days.

Q:

P alone can do a piece of work in 24 days. The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work. How many days are required to complete by P and Q working together ?

A) 9 3/5 days B) 7 days
C) 6 3/7 days D) 8 days
 
Answer & Explanation Answer: A) 9 3/5 days

Explanation:

Let the total work be 'W'

As per the given information,

P can complete the work 'W' in 24 days.

=> one day work of P = W/24

And also given that,

The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work

=> PW/3 = QW/2

=> P's

1 day =    W/24

   ?    =      W/3

=>  ?  = 24W/3W  = 8

=> QW/2 = 8 days

=> Q alone can complete the work W in 16 days

=> P + Q can complete the work in

1/24 + 1/16 = 5/48

=> 48/5 days = 9 3/5 days.

Report Error

View Answer Workspace Report Error Discuss

10 130
Q:

P can do a piece of work in 5 less days than Q. If both of them can do the same work in  days, in how many days will Q alone do the same work  ?

A) 24 days B) 25 days
C) 20 days D) 19 days
 
Answer & Explanation Answer: B) 25 days

Explanation:

Let Q complete that work in 'L' days

=>

=>

L = 25 days.

Report Error

View Answer Workspace Report Error Discuss

7 135
Q:

Time taken by P alone to finish a work is 50% more than the time taken by P and Q together. Q is thrice as efficient as R. If Q and R together can complete the work in 22.5 days, then how many days will P alone take to complete the work ?

A) 17 days B) 11 days
C) 15 days D) 16 days
 
Answer & Explanation Answer: C) 15 days

Explanation:

We know that Time is inversely proportional to Efficiency

Here given time ratio of P & P+Q as

P/P+Q = 150/100 = 3:2

Efficiency ratio of P & Q as

P:Q = 2:1 ....(1)

Given Efficiency ratio of Q & R as

Q:R = 3:1 ....(2)

From (1) & (2), we get

P:Q:R = 6:3:1

P alone can finish the work in

22.5(3+1)/6 = 15 days.

Report Error

View Answer Workspace Report Error Discuss

5 306
Q:

A town having teenagers(boys & girls) of 5000 requires 150 litre of water per head. It has a tank measuring 20 m × 15 m × 5 m. The water of this tank will sufficient for ____ days.

A) 8 B) 6
C) 4 D) 2
 
Answer & Explanation Answer: D) 2

Explanation:

Total Water reqduired = 5000 × 150 lit

= 750,000 litres = 750 cu.m.

Volume of tank = 20 × 15 × 5 = 1500 Cu.m.

Number of days required =1500/750 = 2 days.

Report Error

View Answer Workspace Report Error Discuss

6 183
Q:

Priya can do a work in 16 days. In how many days will the work be completed by Sai, if the efficiency of Sai is 60% more than that of Priya ?

A) 8 days B) 12 days
C) 14 days D) 10 days
 
Answer & Explanation Answer: D) 10 days

Explanation:

Ratio of efficiencies of Priya and Sai is

Sai : Priya = 160 : 100 = 8 : 5

Given Priya completes the work in 16 days

Let number of days Sai completes the work be 'd'

=> 5×16 = 8×d

d = 10 days.

Therefore, number of days Sai completes the work is 10 days.

Report Error

View Answer Workspace Report Error Discuss

9 347