4
Q:

A contractor  undertook a project to complete it in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that  he needed to increase 5 additional  men every 2 days to complete the work in the time the client wanted it:

If the work was further increased by 50% but the contractor continues to increase the 5 workers o every 2 days then how many more days are required over the initial time specified by the  client.

A) 1 day B) 2 days
C) 5 days D) None of these

Answer:   B) 2 days



Explanation:

Total work = 100+50 = 150man-days

In 8 days 100 man-days work  has been completed. Now on 9th and 10th day there will be 25 workers. So in 2 days they wll complete additional 50 man- days work. Thus the work requires 2 more days.

Q:

P is 30% more efficient than Q. How much time will they, working together, take to complete a job which P alone could have done in 23 days?

A) 16 days B) 13 days
C) 15 days D) 12 days
 
Answer & Explanation Answer: B) 13 days

Explanation:

Ratio of times taken by P & Q = 100 : 130 = 10:13

Let Q takes x days to do the work

Then, 10:13 :: 23:x

=> x = 23x13/10

=> x = 299/10

P's 1 day's work = 1/23

Q's 1 day's work = 10/299

(P+Q)'s 1 day's work = (1/23 + 10/299) = 23/299 = 1/13

Hence, P & Q together can complete the work in 13 days.

Report Error

View Answer Workspace Report Error Discuss

10 259
Q:

If 2 men and 3 women can do a piece of work in 8 days and 3 men and 2 women in 7 days. In how many days can the work be done by 5 men and 4 women working together?

A) 3 days B) 6 days
C) 4 days D) 2 days
 
Answer & Explanation Answer: C) 4 days

Explanation:

From the given data,

=> (2 M + 3W) 8 = (3M + 2W)7

=> 16M + 24W = 21M + 14 W

=> 10W = 5M

=> 2W = M

=> 14W × ? = 7W × 8

? = 4 days

Report Error

View Answer Workspace Report Error Discuss

11 329
Q:

28 Men and 52 women working together completes a work in 22.5 days. 35 men and 65 women working together on same work will complete it in how many days?

A) 16 B) 18
C) 19 D) 21
 
Answer & Explanation Answer: B) 18

Explanation:

clearly total persons are increased in => 28/35 :: 52/65 = 4:5

As time is inversely proportional to men, so total time will decrease in the ratio 5:4

Hence, 22.5 x 4/5 = 18 days.

Report Error

View Answer Workspace Report Error Discuss

8 186
Q:

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left?

A) 8/15 B) 7/9
C) 6/13 D) 4/11
 
Answer & Explanation Answer: A) 8/15

Explanation:
P's 1 day's work = 1  
15
Q's 1 day's work = 1  
20
(P + Q)'s 1 day's work = ( 1 + 1 ) = 7  
15 20 60
(P + Q)'s 4 day's work = ( 7 x 4 ) = 7  
60 15
Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15
Report Error

View Answer Workspace Report Error Discuss

7 233
Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days

=> 1 day work of X = 1/10

Y can do in 15 days

=> 1 day work of Y = 1/15

1day work of (X + Y) = 1/10 + 1/15 = 1/6

Given they are hired for 5 days

=> 5 days work of (X + Y) = 5 x 1/6 = 5/6

Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Workspace Report Error Discuss

8 374