Q:

A is thrice efficient as B and C is twice as efficient as B. what is the ratio of number of days taken by A,B and C, when they work individually?

A) 2:6:3 B) 2:3:6
C) 1:2:3 D) 3:1:2

Answer:   A) 2:6:3



Explanation:

                                                       A    :    B    :    C

Ratio of efficiency                    3     :    1    :    2

Ratio of No.of days               \inline \fn_jvn \left \{ \inline \fn_jvn \frac{1}{3}     :    \inline \fn_jvn \frac{1}{1}    :   \inline \fn_jvn \frac{1}{2}  \inline \fn_jvn \left \right \}

     or                                              2    :    6    :    3

Hence A is correct.     \inline \fn_jvn \left [ \because Time \prec \frac{1}{Eficiency} \right ]

Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days

=> 1 day work of X = 1/10

Y can do in 15 days

=> 1 day work of Y = 1/15

1day work of (X + Y) = 1/10 + 1/15 = 1/6

Given they are hired for 5 days

=> 5 days work of (X + Y) = 5 x 1/6 = 5/6

Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Workspace Report Error Discuss

8 247
Q:

If 10 men take 15 days to complete a work. In how many days will 37 men complete the work?

A) 3 days B) 4 days
C) 5 days D) 6 days
 
Answer & Explanation Answer: B) 4 days

Explanation:

Given 10 men take 15 days to complete a work

=> Total mandays = 15 x 10 = 150

Let the work be 150 mandays.

=> Now 37 men can do 150 mandays in 150/37 =~ 4 days

Report Error

View Answer Workspace Report Error Discuss

12 172
Q:

Three taps P, Q and R can fill a tank in 12 hrs, 15 hrs and 20 hrs respectively. If P is open all the time and Q and R are open for one hour each alternately, starting with Q, then the tank will be full in how many hours ?

A) 9 hrs B) 7 hrs
C) 13 hrs D) 11 hrs
 
Answer & Explanation Answer: B) 7 hrs

Explanation:

Given,

P can fill in 12 hrs

Q can fill in 15 hrs

R can fill in 20 hrs

=> Volume of tank = LCM of 12, 15, 20 = 60 lit

=> P alone can fill the tank in 60/12 = 5 hrs

=> Q alone can fill the tank in 60/15 = 4 hrs

=> R alone can fill the tank in 60/20 = 3 hrs

Tank can be filled in the way that

(P+Q) + (P+R) + (P+Q) + (P+R) + ....

=> Tank filled in 2 hrs = (5+4) + (5+3) = 9 + 8 = 17 lit

=> In 6 hrs = 17 x 6/2 = 51 lit

=> In 7th hr = 51 + (5+4) = 51 + 9 = 60 lit

=> So, total tank will be filled in 7 hrs.

Report Error

View Answer Workspace Report Error Discuss

7 361
Q:

P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?

A) 56 days B) 54 days
C) 60 days D) 64 days
 
Answer & Explanation Answer: D) 64 days

Explanation:

(P+Q)'s 1 day work = 1/24

P's 1 day work = 1/32

=> Q's 1 day work = 1/24 - 1/32 = 1/96

Work done by (P+Q) in 8 days = 8/24 = 1/3

Remainining work = 1 - 1/3 = 2/3

Time taken by Q to complete the remaining work = 2/3 x 96 = 64 days.

Report Error

View Answer Workspace Report Error Discuss

6 339
Q:

A can complete 9/10 part of a work in 31 days. After that, with the help of B he can complete the remaining work in 4 days. In how many days will  A and B together can complete that work ?

A) 36 B) 40
C) 42 D) 38
 
Answer & Explanation Answer: B) 40

Explanation:

Remaining work = 1 - 9/10 = 1/10

=> A & B together completes 1/10 of work in 4 days

=> 1 work can completed in ------ ? days

Let it be x days

=>  

=> x = 40 days.

Hence, A & B together can complete the work in 40 days.